Rampal power plant set for December launch

Construction of the first unit of the Rampal coal-fired power plant, located 14km away from the Sundarbans, is almost complete and the plant is expected to be inaugurated in December this year.

“We expect Prime Minister Sheikh Hasina to inaugurate the Rampal Power Plant at the time,” said Md Habibur Rahman, secretary of the Power Division.

The 1,320-megawatt (660*2) power plant is being implemented by Bangladesh-India Friendship Power Company Ltd (BIFPCL). India’s Bharat Heavy Electricals Ltd (BHEL) has been awarded the contract for the Tk160 billion project.

According to a progress report, commercial production of the power plant is commissioned to start in October following a trial run to be held in September.

“As per the latest plan, the plant can start generating electricity at the end of October, or by November at the latest. Officially, the launch is in December,” said Habibur Rahman.

In 2010, a Memorandum of Understanding (MoU) was signed between the Bangladesh Power Development Board (BPDB) and India’s NTPC for the implementation of the Rampal Power Plant Project.

According to the MoU, Rampal was supposed to begin production in 2018. However, the deadline was extended several times for various reasons, including the Covid-19 pandemic.

According to project officials, construction of the project is now progressing at a fast pace. As much as 83% of the project work has been completed and the first unit is almost ready for trial production.

“Physical construction of unit-1 is done and trial production can begin soon,” said a high official of the project.

“Electricity supply to the national grid will be possible by November,” he added.

“If there is no crisis, the second unit is expected to begin production in February 2023,” he said.

Electricity will be supplied to Khulna, Dhaka

According to officials, the electricity generated at the Rampal Coal Power Plant will be supplied to Khulna through the Gopalganj transmission line. Later, when power generation begins in the second unit, electricity will be supplied to Dhaka across the Padma River.

Rampal’s power plant will be connected to Dhaka through a 400 kV transmission line which is under construction from Gopalganj to Aminbazar.

Regarding the transmission line, a high official said it is expected to be completed by February next year. Then the government can begin to supply electricity from Payra and Rampal power plants to Dhaka once the transmission line across the Padma River is complete.

“It was not possible to keep pace in the construction of the transmission line due to Covid-19. Now the construction work is progressing quite fast,” he added.