Banshkhali-Meghnaghat 400kV power transmission line comes into operation

The Power Grid Company of Bangladesh (PGCB) has commissioned its 400kV power transmission line from Banshkhali in Chittagong via Madunaghat to Meghnaghat in Narayanganj.

The 276-km transmission line was commissioned at 5:16pm on Tuesday, the PGCB said, adding that it had been made operational from the Meghnaghat end.

The line will supply electricity from the under-construction SS Power Plant in Banshkhali via Madunaghat of Chittagong to the newly constructed 400/230kV grid substation in Meghnaghat.

Earlier, a 400kV transmission line from Meghnaghat to Dhaka's Aminbazar was commissioned at full capacity on July 23.

As both the lines are connected through the Dhaka-Chittagong 400kV line, the high-voltage power transmission infrastructure has now become more intensified.

The longest 400kV line will serve as the backbone of power transmission between Dhaka and Chittagong.