The 20.1 km-route from Uttara to Motijheel on Bangladesh’s first metro rail became completely visible after the installation of the last girder of the viaduct on Thursday.
The milestone was achieved at 11.14am, when workers successfully installed the last span of the viaduct between pillars no 582 and 583 in front of the National Press Club.
The overall progress of the project stands at 74%, MAN Siddique, managing director of Dhaka Mass Transit Company Ltd (DMTCL), said in a virtual media call.
Also Read- Government plans to build metro rail in all major cities
He said a proposal had been made to increase spending on the project by Tk8,000 crore as the pandemic had been posing a challenge.
“Land acquisition is underway from Motijheel to Kamalapur. Spending has shot up due to increases in the land acquisition cost,” he said.
Mahmud Hossain Opu/Dhaka TribuneThe original cost of the project was Tk 21,985 crore, but project authorities last year sought a further Tk 8,000 crore for additional work, including extension of the line up to Kamalapur and building spacious footpaths outside the stations for convenient entry and exit of passengers.
Also Read- Dhaka Metro: The dream project now demands foolproof security
High-definition CCTV cameras with face detection technology will be installed in the project area, he said, adding that arrangements would be made for people with special needs.
The full section will be operational by December 2023, as per the DMTCL announcement. However, commercial operations on the Uttara-Agargaon section will start on December 16, the country's Victory Day, this year as over 90% of the work of this part has already been completed.
Also Read- Mega dreams on the verge of reality
The Dhaka metro rail is expected to carry 60,000 passengers per hour, traversing the 21.26km from Uttara to Motijheel-Kamalapur Railway Station in less than 40 minutes.