Parts of the Dhaka Elevated Expressway (airport to Moghbazar) will be opened after the second phase of the public-private partnership (PPP) project is completed.
Road Transport Minister Obaidul Quader said this while addressing the media during a project visit on Wednesday.
He said: "The first phase of the PPP project, from Hazrat Shahjalal International Airport to Banani railway station, will be completed by June this year.
"The second phase (from Banani station to Moghbazar railway crossing) of the construction work is expected to be finished in July."
"In the third phase, the expressway will connect Moghbazar crossing to Kutubkhali on the Dhaka-Chittagong highway.
"It will be completed by September 2021,” Quader told reporters after visiting the project site at Kawla near the airport.
The minister claimed that 50% work of the first phase is complete, while the overall progress of the project is 20%.
The 20km Dhaka Elevated Expressway has a budget of Tk8,940.18 crore. It will start from Shahjalal Airport and end at Kutubkhali on the Dhaka-Chittagong highway via Kuril-Banani-Mohakhali-Tejgaon-Moghbazar-Kamalapur-Sayedabad-Jatrabari.
AHM Shakhawat Akhtar, project director, Sakasith Swanagar, manager of Italian Thai Development Public Company Limited, and other officials were also present during the project visit.