Initial deal penned for physical construction of Rooppur plant

The Bangladesh Atomic Energy Commission (BAEC) has signed the third initial deal of $189m with the Russian company Atomstroyexport for the construction of the Rooppur Nuclear Power Project (RNPP).

Acting BAEC chairman Md Monirul Islam and a representative of the Russian atomic energy commission Rosatom signed the agreement titled “performance of first priority construction and the erection work of preparatory stage prior to the first concrete” at the BAEC office yesterday.

“The proposed deal would be sent to the next meeting of the cabinet committee on public purchase for approval,” Monirul said.

A BAEC official, seeking anonymity, told the Dhaka Tribune: “Because of the inefficiency of the Bangladesh team, the deal has been delayed by five months. Although the Bangladesh side wanted to sign the deal for $154m, the Russian side wanted to sign it for $194m. Finally, the deal was signed for $189m following insistence by the Russian side.

“Russia has increased $35m, promising additional equipment,” the official added.

The initial deal has come following negotiations that began between the parties in December.

“We wanted to sign the deal in December but it was delayed because of violent political situation at that time,” Project Director Mohammad Shawkat Akbar told the Dhaka Tribune.

Russia has agreed to provide $500m to finance the initial stages of Bangladesh’s first nuclear power project.

Of the amount, $189m will be spent for performance of first priority construction and the erection work of preparatory stage, prior to the first concrete at Rooppur site.

Around $265m will be spent on the development of design documentation, first priority working documentation and engineering survey for design stage.

Around $45.9m will be spent for the development of feasibility evaluation, environment impact assessment analyses for the RNPP site as the performance of the necessary engineering survey and environmental studies.

The government has appointed Russian consultancy firm Atomstroyexport to supervise and monitor the construction of the plant.

The Russian firm will run a series of 63 tests and as part of pre-construction work it will conduct feasibility evaluation, environment impact assessment and other surveys.

The BAEC, under the Science and Technology Ministry, will implement the project.

Prime Minister Sheikh Hasina inaugurated the groundwork of the 2,000MW plant in Pabna on October 2 last year.

Bangladesh plans to produce 1,000MW of electricity by June 2017 and another 1,000MW by 2022 from the nuclear plant that will have a tenure of 60 years with options to extend up to another 20 years.

Russian State Atomic Energy Commission (Rosatom) will build, operate and provide fuel to the plant and take its waste back to Russia regularly. The total cost of the proposed plant has been estimated at between $5bn and $6bn.

Bangladesh has been considering embarking on a nuclear power programme for over five decades, and Rooppur, about 200km north of Dhaka, was earmarked for the country’s first plant as long ago as 1963.