5,50,000C needed for railway sector overhaul

The government has taken a massive move to upgrade the country's railway network as the sector is considered the safest, most comfortable and most affordable means for transporting passengers and goods. 

Considering the importance of the railway sector, the government wants to implement several projects "to ensure a balanced and integrated development".

All these activities will be done under the Eighth Five Year Plan (2021-2025), which targets to achieve 8.51% GDP growth with yearly 8% growth on average in the next five years. 

The plan also envisages reducing the poverty rate to 15.6% at the end of the deadline, according to an official document, UNB reported. 

Comprehensive steps will be taken for the construction of 798.09km of new railway lines, 897km of dual gauge/double railway lines parallel to existing railway lines, and renovation of 846.51km of the railway network. 

It also includes the construction of nine important railway bridges and other infrastructural development schemes, including level crossing gates, domestic container depots, and the building and modernization of repair and maintenance outlets. 

Moreover, the plan includes the purchase of 160 locomotives, 1,704 passenger coaches and modern maintenance equipment, improvement of the signaling system at 222 stations, and strengthening of railway management. 

Meanwhile, the government is implementing the 30-year revised Master Plan (2016-2045) of the Bangladesh Railway. 

According to the plan, steps have been taken to connect Dhaka with Cox's Bazar, Mongla Seaport, Tungipara, Barishal, Chittagong Hill Tracts, and other parts of the country.

The initiatives include establishing Trans-Asian Railway and Regional Railway Network and connecting important cities with the nearest suburbs by introducing a modern commuter train service. 

The Trans-Asian Railway network, which was initiated in the 1960s, comprises 114,000km of rail routes of international importance. It aims to offer efficient rail transport services for goods and passengers within the ESCAP (Economic and Social Commission for Asia and the Pacific) and between Asia and Europe. 

Under this master plan, 230 projects will be implemented in 6 phases at the cost of Tk5,50,000 crore. 

The overall progress of the Padma Multipurpose Rail Link Project is 58%, and the double-track dual gauge railway bridge construction on the river Jamuna is 40%. 

Around 71% of construction work of the single-line dual gauge track from Dohazari to Cox's Bazar via Ramu and from Ramu to Gumdhum, near Myanmar border, has been completed. 

In addition, approximately 90% of work on the Khulna-Mongla railway project has been completed. Construction work of Rupsha Rail Bridge is nearly completed.

The government has also taken initiatives to build a railway line from Bhanga in Faridpur to Payra Port via Barisal and Patuakhali to connect Payra Port with Padma Rail Link. 

The approval of the revised workforce structure of 47,703 posts is in process. It will help enhance the quality of service, according to the document.