The first unit of Bangladesh’s maiden nuclear power plant at Rooppur has begun supplying 350 megawatts (MW) of electricity to the national grid on a trial basis.
The initial supply began at 3pm on Tuesday in the presence of Science and Technology Minister Fakir Mahbub Anam, the Power Division said in a statement.
The development marks a major milestone following years of work, technical preparations and a series of complex tests to bring the plant into operation.
According to the Power Division, the initial trial connection will last around 8-10 hours, during which the performance and stability of the plant’s turbine, generator and integrated systems connected to the national grid will be assessed.
The plant will then be disconnected from the national grid for further technical tests. After a break of around 28 hours, it will be reconnected for another 4-6 hours to complete the necessary technical and operational assessments.
Relevant sources said the performance of various plant systems, including the turbine and generator, as well as their coordination with the national grid, would be closely monitored at every stage.
Once all tests yield satisfactory results and the scheduled activities for this phase are completed, the plant will require approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) to proceed to the next phase of trial operation.
Subject to regulatory approval, the plant will again be connected to the national grid on a trial basis to continue electricity supply.
Under the agreement with the Russian contractor, the first unit will undergo a 10-month trial operation before beginning permanent commercial electricity supply at full capacity.
Following the successful completion of the trial period, the first unit will be provisionally handed over by the Russian contractor to the Bangladesh Atomic Energy Commission.
The Nuclear Power Plant Company Bangladesh Limited (NPCBL) will subsequently begin operating the plant as its designated operating organisation following a government gazette notification.
The Rooppur Nuclear Power Plant has two units, each with a generation capacity of 1,200MW, giving it a combined capacity of 2,400MW.
The plant is expected to play a significant role in meeting the country's growing electricity demand, strengthening energy security and ensuring a sustainable power supply.