Rooppur’s first power may reach national grid this week

Electricity may begin flowing experimentally from the first unit of the Rooppur Nuclear Power Plant to the national grid this week, with preparations underway. After completing the initial stage of production, authorities are gradually raising the reactor’s power capacity to generate around 300MW.

Commercial production, however, may take around another year, and the price of the plant’s electricity has not yet been finalized. The authorities could not say when it will be determined. No payment is required for electricity supplied on a trial basis.

Power startup phase under way

On October 29, the Bangladesh Atomic Energy Regulatory Authority (BAERA) approved the next phase of work on the first unit, called Power Startup or C-Stage. The activity began at 12:03pm on October 30, with pressure and temperature inside the reactor being increased. This is preparing the heat required for electricity production and the start of the relevant equipment.

Plant officials said the C-Stage target is to gradually raise the reactor’s capacity to 25-30%. During this period, the functionality of the reactor, cooling system, turbine, generator, electricity supply and control systems will be tested. These tests will confirm whether the plant can be operated safely and stably at different capacities. Once capacity reaches 25-30%, it may be possible to generate around 300MW and supply it experimentally to the national grid.

A plant official, speaking on condition of anonymity, said: “Preparations are underway. Electricity may even be connected to the national grid tomorrow, Tuesday. However, since this is a technical matter, I am not saying this with certainty.”

BAERA Chairman Mahmudul Hasan recently said the entire process would be monitored after electricity was supplied experimentally to the grid, to check that everything was proceeding properly. After tests and monitoring confirmed there were no problems or defects, the plant would be formally inaugurated.

Commercial supply needs more time

Asked when consumers would receive electricity from the plant, officials said various tests could continue for seven to eight months after experimental production begins. During this period, the plant’s equipment, safety systems and capacity to supply electricity to the national grid would be assessed.

Connecting the generator to the national grid, known technically as synchronization, is an important milestone. Officials said commercial production will not begin immediately after experimental production starts. It must first be confirmed that the plant is operating reliably at different capacities, and the necessary approvals must then be obtained before commercial operation.

Earlier, the first nuclear reaction took place at the first unit for the first time on October 11. Although there were plans to begin this activity in September, it was postponed after defects were detected during tests of the safety valve. The necessary tests were later completed and BAERA approval was obtained.

Electricity price still not finalized

Although preparations for supply are progressing, the purchase price of the electricity has not yet been finalized. The Bangladesh Power Development Board’s (BPDB) initial estimate was Tk6.72 per unit. However, costs have increased because the plant could not begin production within the scheduled timeframe, and relevant officials believe this could raise the price to around Tk10.

The company formed for the plant has submitted a proposal to the BPDB for signing a Power Purchase Agreement (PPA). Several rounds of meetings have been held, but final discussions on price determination have not been completed.

BPDB Chairman Engineer Rezaul Karim said the board had sought detailed information on the plant’s project costs and operation and maintenance expenses. These details are being examined and reviewed, and the price will be determined afterwards.

Government power plants are operated under the cost-based method, meaning the price per unit of electricity is determined based on the cost of constructing the plant.

Fuel arriving from Russia

As part of preparations to launch the two units, nuclear fuel uranium is regularly arriving from Russia. Most recently, at around 5:30am on November 14, the fuel was transported to the project area on three specialized lorries under tight security. This is the fifth consignment for the second unit. Including one consignment brought for the first unit, six consignments have so far reached Rooppur.

The Rooppur Nuclear Power Plant, under construction on the bank of the Padma River in Ishwardi upazila of Pabna, has two units with a capacity of 1,200MW each. Once both are fully operational, a total of 2,400MW will be added to the national grid. Russia’s contractor company Atomstroyexport is constructing the plant.

The current project cost is Tk138,686 crore, an increase of around Tk26,000 crore due to the depreciation of the taka against the dollar. The project duration has been extended until June 2028.