The Chittagong-Cox's Bazar railway project has suffered extensive damage due to waterlogging and flooding triggered by torrential rain for the last few days.
In many places of the railway project, water was flowing under the railway line.
In some places, the stones of the railway line have washed away, and the bridge has collapsed.
However, the extent of the damage could be assessed once flood water recedes, said officials related to the project.
Meanwhile, the local residents claim that the flood situation in South Chittagong has become dire due to the railway project.
Heavy rains have caused extensive damage to the under-construction bridge over the Patiya Shrimai canal. The railing of the bridge fell down.
Patiya Railway Station Manager Nizam Uddin said: "The bridge has been damaged by the flood. The matter has been informed to the officials. It is looked after by the mechanical department of the railways.”
Dohazari-Ramu-Cox's Bazar Railway Project Director Mofizur Rahman said: "Due to incessant rains, severe floods have occurred in Chittagong and Cox's Bazar. We know that the railway line has been damaged. But what kind of damage has been done will be known after the water recedes.”
He also said the rail track in Satkania near Bandarban has been mostly affected.
He also said: “Already 90km of Dohazari-Cox's Bazar railway line is visible. Besides, 87% of project work has been completed. Preparations are being made to run the train by completing the railway line work by next September. The construction work halted for the past few days due to floods. The water is receding now. The places where there are cracks will be repaired.”
Enamul Haque, a resident of Keuchia Union of Satkania Upazila, said that there has been extensive damage in south Chittagong due to this flood.
Millions of people were marooned in water. Due to the unplanned construction of Dohazari-Cox's Bazar railway line, the flood situation has become so dire. People have suffered and damage increased. The railway line has been built as high as an embankment, due to which the flow of water was blocked, he blamed.
There are also not adequate culvert-bridges. Because of this, the flood situation has worsened.
The under-construction rail line is scheduled to open by September this year, said Railways Minister Nurul Islam Sujan on May 16.
On April 3, 2011, Prime Minister Sheikh Hasina laid the foundation stone for the construction of meter-gauge railways from Dohazari to Ramu-Cox's Bazar and Ramu-Ghumdhum.
The project comprises 88km from Chittagong's Dohazari to Ramu and an additional 12km from Ramu to Cox's Bazar.
The construction of a dual gauge and single track railway project started in 2018, almost seven years after the inauguration by the prime minister.
Initially estimated to cost Tk1,852 crore, the construction of the 100km railway line from Dohazari to Ramu in Cox's Bazar saw a revised project proposal in 2016, resulting in an increased cost of Tk18,034.47 crore.
The project is being financed by the Asian Development Bank (ADB) and the government of Bangladesh.