Padma Bridge: Will train services start this year?

Uncertainty looms over the inauguration of train services between Dhaka and Faridpur through the Padma Multipurpose Bridge within this year as around 45% of the project work is still incomplete.

Earlier, the government moved away from the decision of opening rail link and road communications on the long-cherished Padma Multipurpose Bridge for the public on the same day, likely by June 30 this year.

The government took the decision as the Mawa and Bhanga section of the Padma Bridge Rail Link Project (PBRLP) is not ready to be launched along with the Padma Bridge for traffic. 

Consequently, Bangladesh Railway (BR) set a new target to open the Dhaka and Faridpur (Dhaka-Mawa and Mawa-Bhanga sections) rail link within this year through the Padma Bridge.

However, the Mawa and Bhanga section of the project witnessed 71% progress while that on the Dhaka-Mawa section was only 41%. Altogether, the progress of the project was around 55% till December 2021.

Reason behind delay

According to the BR, the Bridges Division has yet to hand over the railway section of the Padma Bridge. They will not be able to hand it over before March this year as work on the gas pipeline is being delayed.

BR officials say the delay in the handover of the project interrupted the completion of the project.

“We have done a series of meetings with the authorities concerned, including the Bridges Division, to hand over the bridge to finish our work. But we didn’t get notification of clearance from Bridge Authority as the road portion of the bridge is being prioritized so far,” said Railway Minister Nurul Islam Sujan.

"Once the rail portion of the bridge is handed over to us, it will take another six months to complete the rest of the work. So, it will not be possible to operate trains on the bridge in June," he added.

According to the Bridge Division, it is yet unclear when they will be able to give the NoC (No Objection Certificate) to the BR but it is decided that it will not be possible before April.

Although the revised deadline of the railway project is 2024, progress of all the segments is below target, according to the BR.

PBRLP was approved in March 2016 at an initial estimated cost of Tk34,989 crore.

The physical work of the project commenced only in July 2018, mainly due to the delay in signing of the loan contract with Chinese Exim Bank. In the meantime, the project cost climbed to Tk39,246 crore.

Minister still hopeful

Railway Minister Nurul Islam Sujan is still optimistic about operating trains through the Padma Bridge by this year.

He told Dhaka Tribune: “As it is not possible to open train service on the first day of opening the Padma Bridge for traffic, we set a target to start train service from Dhaka to Faridpur’s Bhanga in December 2022.”

The minister said setting a target is very important. “If we have no target, how could we evaluate the progress?”

People will get no benefit if the train is operated from Bhanga to Mawa. On the other hand, if it is operated from Dhaka to Bhanga, people can get a meaningful service, according to the rail minister.

“It is very common for the railway to miss deadlines and make wrong decisions,” said Prof Moazzem Hossain of the Civil Engineering Department of Bangladesh University of Engineering and Technology (Buet).

“Political intention is very important to complete a project as per target,” he added.