Second railway span on Padma Bridge viaduct installed

The second railway span was set up on the viaduct of the much-hyped Padma Bridge on Monday.

Local and foreign engineers placed the J-04 railway span between the pillars N-21 and N-22 at the Jazira end in Shariatpur.

A total of 14 railway spans, seven each in Mawa End and Jazira End, will be installed on the bridge. 

The length of each span is 38 metres, comprising six I-girders. A total of 84 girders will be set up on the rail viaduct on both sides of the Padma Bridge, said several associate engineers of the project.

Ahsan Ullah Majumdar, assistant engineer in the Padma Bridge project, said: “We are going to install 14 spans in total with 84 I-girders in Mawa and Jazira end of the bridge. The work started from Saturday and we are hoping to finish the process soon.”

The 13th span (superstructure) of the 6.15km bridge has been installed at its Jazira end, making 1,950 metres or 1.95km of the much-hyped bridge visible.

Railway spans are also being installed on the viaduct of the Padma Bridge, the first in Bangladesh. After getting six I-girders, a span gets the shape. With the help of the crane, these railway spans are pulled to the height of the pillar.

Assistant Engineer Humayun Kabir said: “We installed 320 railway slab tracks, and 28 roadway slab tracks earlier. We have already completed the construction of 28 out of 42 pillars. We are halfway through the construction of the mega project.”

According to the Ministry of Railways, the Padma Bridge Rail Link Construction Project will establish a rail link between Mawa and Bhanga via Jazira and Shibchar, through the Padma Multipurpose Bridge.

It will connect Dhaka, Narayanganj, Munshiganj, Shariatpur, Madaripur, Faridpur, Gopalganj, Narail, and Jessore.

The Chinese government-nominated contractor, China Railway Group Limited is implementing the project under China G2G system. Under the project, 23km ballast-less elevated viaduct rail line will be constructed. 

On the elevated viaduct, two platforms – one mainline and two loop lines – will be constructed along with installation of lifts.