Legal issues delay development at Purbachal project

The development activities of the Kaliganj portion of Purbachal New Town Project in Gazipur has been moving at a snail’s pace as the project awaits the Supreme Court’s verdict on the legality of the housing project.

Although officials at the Rajdhani Unnayan Kartripakkha claimed that the project work had been progressing as per schedule, local residents, former land owners and winners of the plot lottery alleged that the development work in the area had been irregular.

When asked, Rajuk Deputy Director (Estate 3) Ahsan Iqbal Bhuiyan told the Dhaka Tribune: “The development work of the project faced a little delay after the writ petition filed by the Bangladesh Environmental Lawyers Association (BELA). Already, the Supreme Court has announced a verdict in our favor, allowing us to continue to run the project.

“The development activities are still going on and will resume full swing after the  Supreme Court’s final verdict.”

Meanwhile, Rajuk Legal Officer AKM Maruf Hasan said: “The housing project is not harmful for the environment, reasoning the SC has vacated Bela’s writ petition from several months ago.

“An open court directed that Rajuk can continue the development work alongside conserving the forest in the project area. So, the development is still going on.”

Maruf, however, claimed though Rajuk did not get a certified copy from the court and did not start the development work in full swing.

Answering a question regarding the plot owners’ concerns, he said: “Rajuk has not made a new decision or change in the project area and every plot winner will get the allotted plot in the housing project.”

He said: “The plot winners could also register their plots by paying in installments or making the full payment.”

On November 25, 2013, the Supreme Court directed Rajuk to maintain status quo on the construction work of the Purbachal project at Barokau and Parabartha moujas in Kaliganj upazila of Gazipur.

The status quo came after Rajuk filed a plea following a High Court verdict which asked Rajuk to suspend the project until it obtained a clearance certificate from the Department of Environment.

The HC verdict came following a writ petition filed by Bela against the housing project on April 18, 2013.

On August 20, the chamber judge of the SC stayed the high Court order. Later, Bela filed the petition with the SC to vacate the chamber judge’s order.

During a recent visit at Barokau and Parabarthha moujas, the Dhaka Tribune found that the development work in the area had stopped after the lowlands were filled up with sand. No other infrastructural development has been started.

Locals also claimed that Rajuk had started the development work in the area about one month ago, but failed to continue it in the face of protests by land owners.

Rajuk officials said as per the revised project schedule, some 24,697-plots in 30 sectors of the project will be completed by December, 2015. Earlier, the project was expected to be finished by June 2012.

In 1992, the government drafted the formation of a planned satellite city – Purbachal New Town – and stated acquiring land for the project in 1993. The project is situated at Rupgonj upazila of Narayanganj and Kaliganj upazila of Gazipur between the Balu and Sitalakhya rivers on the north-east side of Dhaka.