The first ever metro rail of the country will begin carrying passengers in the capital by December 2022 with the Uttara North-Agargaon stretch, Dhaka Mass Transit Company Limited (DMTCL)Managing Director MAN Siddique said on Tuesday.
The DMTCL is the implementing body of the project.
All the relevant test runs on the Uttara North-Agargaon segment of the Mass Rapid Transit (MRT) Line-6, which runs from Uttara North-Kamalapur, and other work is expected to be completed by that time, he said.
Siddique, however, was cautious with respect to the timeframe, referring to the ongoing Covid-19 pandemic.
On a press tour in Uttara on Tuesday, organized by the embassy of Japan in Bangladesh, it was seen that work was progressing, including test runs and other relevant activities. A select group of journalists was taken to the under-construction Uttara North station, where they were given a demonstration of a running train and given access inside the train to see the interior and other amenities.
Japanese Ambassador in Dhaka Ito Naoki, former captain of Bangladesh cricket team Habibul Bashar, former member of the Bangladesh cricket team Abdur Razzak, and current member of the national cricket team Mehidy Hasan Miraz were present, among others.
“We are not facing the challenges we did a few months ago due to the pandemic. If the situation does not get worse, we will be able to have commercial operations commence by December next year,” the DMTCL chief said.
To a question, he said the government would not look for profit from the commercial operations of the metro rail at the beginning.
Siddique said there would be a total of nine stations between Uttara North and Agargaon, and work was continuing with the current focus on the upper levels.
There are currently seven trains, each comprising six coaches, engaged in trial runs. There is also one at the Mongla Port and another one will arrive in the next month, journalists were told.
In total, 24 trains with 144 coaches will be used for the MRT Line-6.
After the commencement of commercial operations, there will be one train every three-and-a-half minutes, with each train carrying nearly 1, 800 passengers. The Uttara North-Motijheel segment of the MRT Line-6 is expected to be completed by 2024, while no target has been fixed for the Motijheel-Kamalapur stretch.
Speaking on the occasion, Japanese Ambassador Ito Naoki said there had been steady progress in the work despite the outbreak of the Covid-19 pandemic.
“Once completed, the Dhaka metro rail will usher in a new era,” he said.
Representatives of the Japan International Cooperation Agency (JICA), which is providing loans toward the completion of the metro rail project, and other Japanese commercial entities involved with the project also spoke on the occasion.