Mainline performance test of metro train in August

Bangladesh’s first overhead metro train, the country’s latest communication system undertaken by Prime Minister Sheikh Hasina, will start its mainline performance test on the viaduct in August.

“We will begin mainline performance test on the viaduct in August after functional test, which is being carried out inside the depot,” Dhaka Mass Transit Company Limited (DMTCL) Managing Director (MD) MAN Siddique told BSS on Monday.

He said that the integrated test will be carried out after the mainline performance test on the viaduct and then the trial run of the first metro train will be conducted.

Meanwhile, the second set of metro train reached the depot 15 days ahead of the schedule, Siddique added.

He said the construction of all metro stations was going on in full swing amid the coronavirus pandemic with maintaining health guidelines strictly.

According to the project details, the third and fourth shipment of the metro train set is scheduled to be done on June 11, which will reach the country on August 13. The fifth set will start its journey from Japan on July 16 and is expected to reach Bangladesh on September 17.

The real progress of this package is 44.91%.

It said the civil work progress of the first phase construction of metro rail from Uttara to Agargaon is 85.74%, the second phase progress from Agargaon to Motijheel is 62.50%, and the coordinated progress of electrical and mechanical system and rolling stock (rail coach) and procurement of depot equipment stood at 56.04%.

Besides, platform construction of Uttara North, Uttara Centre, Uttara South and Pallabi stations were completed, while platform construction of Mirpur 11, Kazipara and Shewrapara stations are going on.

The metro rail is projected to carry 60,000 passengers per hour by travelling the entire route of 21.26 km from Uttara to Motijheel-Kamalapur Railway Station in less than 40 minutes.

The project details also said if the current pace of work continues by following safety rules during the ongoing coronavirus situation, the rail project might be completed within December 2022.

The length of the metro rail route up to Motijheel was 20.10 km. But now it is extended by 1.16 km to Kamalapur Railway Station. As a result, the number of stations has also increased to 16.

To deal with the ongoing coronavirus pandemic, a 10-bed isolation centre (Field Hospital) at the Gabtoli construction site and a 14-bed isolation centre at Uttara Ponchoboti construction yard were constructed, said DMTCL MD Siddique.

He said persons infected with Covid-19 were kept either in home or institutional quarantine and if needed, they were admitted to a dedicated hospital.

The project details said there will be a total of 16 stations of the Mass Rapid Transit-MRT Line-6.

The stations are – Uttara North, Uttara Centre, Uttara South, Pallabi, Mirpur 11, Mirpur 10, Kazipara, Shewrapara, Agargaon, Bijoy Sarani, Farmgate, Karwan Bazar, Shahbagh, Dhaka University, Bangladesh Secretariat and Motijheel.

The iconic stations will be at Diabari, Mirpur and Motijheel, while others stations will be constructed ordinarily.