After failing the main deadline to install 200,000 prepaid meters across Dhaka city, Titas Gas Transmission and Distribution Company Limited (TGTDCL) now seems determined to complete the project by December 2019, a year before the actual 2020 deadline.
Not only that; it is now considering undertaking another project of installing 120,000 more prepaid meters, mainly in the capital’s southern part.
Till November, it installed 196,700 meters in Dhanmondi, Mohammadpur, Sher-e-Bangla Nagar, Mirpur, Kafrul, Cantonment, Khilkhet, Gulshan, Banani, Baridhara, Bashundhara, Uttara, Uttar Khan, Dakshin Khan, Uttara, Badda, Rampura, Tejgaon, Khilgaon and Motijheel.
It completed 98.35% work of the project till last month at an abnormally high pace, after merely completing one-third of the project in the first three years.
The three-year project to install 200,000 prepaid meters was launched in January 2015, with a deadline of December 31, 2018.
Due to the snail’s pace of the progress, the Energy Division extended the project deadline by two years through a revised development project proposal (DPP) on June 30, 2018.
Since then, the project gained momentum as its officials set a target of installing at least 10,000 meters each month.
As of January 30 this year, the installed meters numbered 85,000, clearly showing that it on average more than 13,000 meters were installed each month until November 30.
According to the TGTDCL’s annual report for the fiscal year 2018-19, some 141,976 meters were installed until June 30.
The report, unveiled on December 10, further said the gas company spent 5.41% more than its budget of Tk 131 crore for the project in the last fiscal year.
Md Faizar Rahman, the metre installation project’s director, last year told Dhaka Tribune that the sluggish progress of the project in the first three years was due to the delayed start of the project.
“The main work started more than two and a half years after the launch of the project,” he added.
But the same official later changed his claim, saying that it was the consumers’ lack of interest in installing prepaid meters, which slowed down the project.
“At the beginning, very few people showed interest in prepaid meters. But over the course of time, their interest grew, resulting in the speedy implementation of the project,” he told the reporter on Thursday.
Titas has installed prepaid meters which are not available in the market, charging Tk60 as monthly fare.
A household consumer having a prepaid meter will have to pay the money for up to 20 years.
When contacted, M Shamsul Alam, energy adviser to the Consumers’ Association of Bangladesh (CAB), said the gas company was doing it all to make a quick buck by installing the meters.
They are robbing the people in the pretext of installing prepaid meters, he alleged, questioning: “Why does the gas company purchase and install the meter on its own?
“Why doesn’t it allow the users to buy the meters from the market?”
When asked if there was any bar from the Bangladesh Energy Regulatory Commission (BERC) regarding realizing the meter fare, an official from Titas official replied in the negative.
BERC member (gas) Abdul Aziz Khan, also a former TGTDCL managing director, when contacted, said he was unaware of any bar from BERC regarding realizing the meter fare.
It is mentionable that a bar is in place for prepaid electricity meters. BERC, in a 2017 order, asked the electricity companies not to charge any fare for using prepaid meters.
About the project
Being the country’s biggest company, Titas undertook the project at an estimated cost of Tk712.099 crore, which was reduced through the revised DPP to Tk498.94 crore.
The lion’s share of the cost is being funded by the Japan International Cooperation Agency (Jica), which is contributing Tk440.68 crore. The rest of the money, Tk56.92 crore, is coming from the government.
Titas is providing only Tk1.34 crore, according to the annual report.
Titas struck an agreement with UK-based consultancy firm Pegasus-Global Holdings Inc on October 7, 2015, to implement the project, with the British firm starting consultancy 12 days later.
On March 16, 2017, the gas company signed another agreement with Toyokeiki Company Ltd, an engineering, procurement and construction (EPC) contractor based in Japan, to implement the project. Toyokeiki started working on September 17, 2017.
120,000 more meters in the offing
Faizar said Jica was willing to extend the project to install another 120,000 prepaid meters in 18 months.
He said that, if finalized, the installation may start from April, adding: “Jica will start working on the extended project under the existing terms, conditions and expenditures.
“The extension may be finalized within this month,” he hoped.