Government plans open-pit mining at Barapukuria

The government plans open-pit coal mining at northern part of the Barapukuria coal field in Dinajpur to use coal from the mine to increase power generation.

A 1,300MW coal-based power plant will be built at the mine’s mouth which will use coal from the mine.

Water modelling and hydro-geological survey were now being conducted at the site to determine the flow of underground water for extracting coal through open-pit mining, State Minister for Power and Energy Nasrul Hamid yesterday said.

“If we get positive results from the water modelling and geological survey, the report will be completed by September and a decision will be made in favour of open-pit coal mining,” he told reporters after a meeting with deputy commissioners (DCs) at the Bangladesh Secretariat.

He said: “We have also planned to build a 1,300MW coal-based power plant at the mouth of the mine. The construction of the plant will require at least five years.

“So, we have to work parallelly for both the projects.”

Prime minister’s Adviser Tawfiq-e-Elahi Chowdhury said: “We have advised the DCs to help power distribution companies to collect due electricity bills and requisition land for constructing new power line and the power plant.”

Requesting anonymity, a deputy commissioner, who attended the DC conference, told the Dhaka Tribune that several DCs had urged the government to provide uninterrupted electricity as they were helpless facing public protest centring frequent load shedding.