A body of ministers yesterday approved a proposal for constructing a 400MW gas-based power plant at Bibiyana in Habiganj.
With Finance Minister AMA Muhith in the chair, the cabinet committee on public purchase also approved the overhauling of a troubled unit of the Ghorashal Power Plant in Narsingdi.
It took the government four years to finally get the work at Ghorashal rolling because international contractors did not show much interest.
For the Bibiyana plant, the government will be using the special Energy Development and Maintenance Fund for the first time.
In September 2013, the World Bank agreed to fund the re-installation of one of the units of the Ghorashal Power Plant.
The Power Development Board (PDB), under the Ministry of Power, Energy and Mineral Resources, will implement the projects.
The Tk2,239.74 crore work for the 400MW Bibiyana plant was awarded to Isolux Ingenieria SA Spain and Samsung C&T Corporation, a Spain-South Korea joint venture.
They lowest tender bidders are supposed to take 900 days for the project, including 720 days for building a simple cycle.
Mustafizur Rahman, additional secretary of the Cabinet Division, told journalists after the meeting that the Bibiyana project would be completed in three years.
The Tk234.61 crore overhauling work has been given to Russia-Ukraine joint venture consortium of Rao-Engineering and LLC Kharkovenergoremond.
Four years ago, after an accident, a PDB probe team found that a unit was at risk because it had not been renovated in 20 years since its inception; as a result the capacity dropped from 210MW to 190MW.
The report submitted by the probe team four years ago expressed fears that a disaster might happen any time unless it was repaired.
According to a Power Division proposal, the Ghorashal plant worked for more than 1.58 lakh hours from 1994-2014.