Shahbagh underpass remains a distant dream

The construction of the much-awaited underpass at the capital’s Shahbagh intersection hangs in a limbo as the Dhaka South City Corporation (DSCC) failed to start the project due to insufficient funds.

The project, which had long been demanded by the students of Dhaka University following frequent accidents at the intersection, had been reportedly shelved as the government plans to build a footbridge at the crossing to save money.

After a series of violent protests by the university’s students following the death of a student crushed under the wheel of a bus at the intersection in August 2012, the DSCC took the initiative to build an underpass at the crossing and the foundation stone of the project was laid on November 26, 2012 by the then state minister for LGRD and Cooperatives Jahangir Kabir Nanok.

The former state minister also said the underpass construction would start from December 15 of the same year and was to be finished within the next six months.  The 50-metre proposed underpass was expected to connect the road between Bangabandhu Sheikh Mujib Medical University and the National Museum.

A DSCC official, seeking anonymity, said during a meeting  between Local Government Department (LGD) and DSCC officials held few months back, the LGD directed DSCC officials to conduct a pre-feasibility study for a foot-over bridge at same location of the proposed underpass.

When contacted, DSCC Chief Executive Officer Md Ansar Ali Khan told the Dhaka Tribune: “The government has changed its decision to build an overpass instead of an underpass.”

He said the total budget for the project was estimated at Tk40 million, but the cost of the project hiked when Dhaka Power Distribution Company (DPDC), Dhaka Water Supply and Sewerage Authority (DWASA) and Titas Gas demanded some Tk 200 million for replacing their utility lines under the road.

“It is not possible to meet the demands of utility agencies under the budget this project.”

Another senior DSCC official said: “Noting the additional funds demanded by other state agencies, the LGD directed the city corporation to visit the project area and plan for an over bridge. Final decision will be taken by the LGD.”

When contacted, LGD Additional Secretary Ashok Madhav Roy told the Dhaka Tribune: “We already discussed on taking steps to build an underpass during a meeting.”

Responding to a question, he said the LGD only directed the DSCC authority to visit the project area and report to them scope of an over-bridge for the same location of the proposed underpass.

“We had not changed our decision on the underpass project. The final decision will be taken after the city corporation report,” he added.