Only 50% of the construction of the Purbachal Link Road has been completed during 14 years since the project was first initiated by Rajuk, as authorities concerned repeatedly shifted responsibility of the project to different agencies and contractors
The snail’s pace of the project, wrong choices in appointing contractors and repeated suspensions of construction work have allegedly been caused by indifference from the state agency Rajdhani Unnayan Kartripakkha (Rajuk).
Rajuk originally initiated the construction of the road in 2000 to connect the satellite city Purbachal with the capital, with the proposed road supposed to make commuting easier in the northeast parts of the city.
The road was also planned to improve the capital’s road communications with Chittagong, Sylhet, Narsingdi, Narayanganj, Munshiganj and other northern and eastern districts, in a bid to save time and huge amount of money every year.
Earlier in 2000, Rajuk initiated the construction of the link road, while in 2004, the Roads and Highways Department (RHD) was tasked with its construction. However, Rajuk took charge of the project in mid-2008 after the RHD failed to make progress.
Later in 2010, Rajuk decided to construct the road with funds under the Purbachal New Town Project at a cost of Tk350crore.
Rajuk officials said the construction of the 300-feet wide Purbachal Link Road started in October 2011 and was scheduled to end last April, while the deadline was later extended to August of the same year.
The under-construction 13.3km link road has been divided into two lots;with the lot 1 consisting 6.9kmof road from Balu bridge to Kanchan bridge on Shitalakkha, while the lot 2 consisting 6.4km of road from Kuril flyover to Balu bridge.
The contractors have reportedly halted construction demanding additional funds as cost adjustment for the rising price of building materials.
The suspension of the construction came at a time when the link road assumed a far greater importance than previous times following the inauguration of the Kuril flyover, as one of its ramps was linked to the Purbachal link road, and another face of the road was linked with the Dhaka bypass road in Rupganj.
ZahirulAlam, a resident of Dumni, said hundreds of people used the link road daily to save time.
“People living in Kuril, Khilkhet, Barua, Dumni, Isapura, Rupganj and different adjoining areas are using the road as a shortcut,” he said.
Zahirul also said the incomplete and bumpy road allows only CNG-run auto-rickshaws and battery-run three-wheelers to operate on the road, adding: “Drivers charge Tk70 as fare for each trip from Khilkhet to Kanchan Bridge.”
Jahanara Akhter, another Dumniresident, said travelling on the potholed road was uncomfortable, especially for the children and the elderly people.
Uzzal Mallick, project manager of Rajuk, told the Dhaka Tribune: “Rajuk has cancelled contracts with former two venture companies – CTCL-Monico of lot 1 and ACL-RP Construction of lot 2 – for the delay of construction.
“Rajuk cancelled contract with ACL-RP Construction in September last year, and also cancelled contract with CTCL-Monico this month,” he added.
Uzzal said construction for lot 2 has restarted after Rajuk signed new contracts with two joint venture companies NCEL-FF CRUZ in December last yearfor the cost of around Tk142 crore. No new contract, however, has been signed for lot 1, he added. Answering to a query, he said around 50% of the construction has been completed.
Rajuk Chief Engineer (implementation) Md Emdadul Islam admitted that the construction has been suspended, adding that agreements with the former contractors had been cancelled because of delays in construction.
Rajuk officials said the 12-lane road is planned to have a four-lane expressway with two service roads on its both sides, as well as seven bridges, six underpasses and two culverts.
During a visit to the project area, the Dhaka Tribune found that although the road was incomplete, the bridges and culverts were almost completed. The new construction companies have also started work on lot 2.