Unless there is a clear shift towards coal or gas-based generation from the existing dependence on costly fuel oil, keeping consumers happy with the price of electricity and simultaneously reducing subsidy to ease pressure on finances will be a daunting task for the government.
For running fuel oil-fired plants, the last government has raised subsidy by over 450% on fuel oil since 2010. Moreover, retail power prices were increased in six phases during the government’s previous term as one of the ways to cut down on subsidy.
The power sector has been getting over Tk5,500 crore allocation annually as subsidy. In FY2009-2010, subsidy in the sector was Tk994 crore which jumped to Tk4,000crore in the following fiscal.
A large part of the subsidy was consumed by the fuel oil-powered quick rental power plants, according to official sources.
According to the Power Division, a unit of fuel oil-fired electricity costs Tk16-20 while gas-fired power costs below Tk2 and coal-fired about Tk6.
Official data shows that the average retail price of per unit of electricity has been raised by 50% from Tk4 to Tk6 over a two and half-year period from March 2010 to September 2012.
Recently, the five state-owned electricity distribution companies proposed further increasing retail power tariff by 8.58% to 23.50% per unit. They urged the Bangladesh Energy Regulatory Commission (BERC) to make the proposed rate effective from March 1.
Because of a shortage of cheaper primary fuels such as gas and coal, the government could not ease reliance on costly fuel oils although it claimed to have raised generation capacity to over 10,000 megawatt.
Professor Shamsul Alam, adviser of the Consumers Association of Bangladesh, said: “Keeping price of power at the present and lowering subsidy at the same time will be a steep challenge. It would be even steeper as the government is focusing more on setting up new power plants instead of discovering new gas fields.
“As a result, the government has to keep on depending on the fuel oil-based plants. That will definitely lead to higher power prices,” he said.
With the overall gas generation nowhere near encouraging – partly because no significant gas reserve has been discovered in recent times – the government had no other option but to extend the costly contracts with the fuel oil-based power stations because elongated periods of darkness in the households will turn out to be immensely unpopular.
Then again, the government cannot continue to rely on fuel oil-based plants for indefinite periods of time and keep mounting pressure on its finances because charging the entire rental on the consumers would take power prices beyond their affordability.
The more the government delays in coming up with the much awaited national coal policy, the more it seems to be the magic wand for the country’s power sector that, if aptly laid out, can be the answer to most of the prevailing and future crunches.
During its previous five-year tenure, the government initiated a number of coal-fired plants; but all those plants could move only as far as the laying of foundation stones.
Chances are thin that these coal-based plants will be able to contribute anything significant in near future because such a plant needs five to seven years to come to operation.
Power Division sources said power generation shortfall hovers around 1,000-1,200 MW every day because of poor gas supply.
Bangladesh, whose 62% of total population enjoys power coverage at present, is witnessing 8-10%annual rise in demand for power.
People get better power now compared to five years ago, but at higher prices. Moreover, load-shedding situation has not improved significantly either.
The government has chalked out ambitious plans for the power sector which require big funding. But gathering the funding too remains a challenge.
An amount of $10bn will be required to produce the targeted 10,000 megawatts of electricity by the year 2018, said a top official of the Power Division.
Of the 10,000 MW, gas-based plants will produce 4,616 MW, for which around 950 million cubic feet of gaswill be needed daily.
According to the Petrobangla, the present recoverable gas reserve of the country is 15.32 trillion cubic feet while the annual consumption amounts to nearly 1tcf. The present reserve can supply gas for 15 years and is not sufficient to meet the additional demand of the gas-fired power plants.
“No progress in the implementation of the coal-based plants is a failure of the government,” said Ijaz Hossain, a professor of Buet.
Ijaz also said supplying gas and coal as primary fuels to generate electricity was another challenge because some proposed plants would have to rely on imported coal.
While talking to the Dhaka Tribune, he suggested that focus should be shifted to extracting indigenous coal.
“If we depend on imported coal to run our power plants, we cannot reduce power prices,”said Professor Ijaz.