Gulshan Lake development bogged down

The improvement and beautification scheme of the Gulshan-Banani-Baridhara Lake in the city was delayed and missed its deadline as Rajuk could not complete acquisition of land and failed to recover land from illegal possession.

The three-year improvement scheme undertaken by Rajdhani Unnayan Kartripakkha (Rajuk) with an estimated value of Tk4.10bn, was approved by the Executive Committee of National Economic Council (Ecnec) on July 6, 2010. It was supposed to start in July 2010 and finish by June 2013.

The scheme sought to reclaim the lake from illegal occupation and preserve the water retention capacity of the lake as well as its beautification.

However, visiting the Gulshan-Banani-Baridhara Lake area recently this correspondent a found that many illegal encroachments were still intact around the lake. Only a small area of the lake had been filled up for building a 2.5km driveway along the eastern side, starting behind Gulshan Shooting Club and ending at Mariam Tower just behind the US embassy.

Sewerage pipe lines were found discharging sewerage into the lake.

Officials of the Rajuk said the authorities were yet to recover about 11 acres of acquired land adjoin area of Gulshan-Baridha Lake due to protest and litigations of occupiers. Moreover, the state-owned agency was yet to acquire 69.14 acres of land, of which 23.58 acres are owned by BTCL and 23.58 acres are publicly owned.

Md Nurul Islam, the executive engineer of Rajuk, told the Dhaka Tribune: “Acquisition of additional land for the project is going on. We have contacted BTCL to acquire their land. For this reason we have not been able to start the development work in full swing.”

He also attributed the delay in work and crossing the deadline to land recovery and pending court cases.

“The development will start after completing the acquisition and recovery of land,” he added.

According to the project plan, a road will be constructed to connect the Gulshan Lake site with Hatirjheel. Starting at Baridhara Circle the road will end at Hatirjheel Police Plaza Concord, passing Mariam Tower, Shahajadpur and Badda.

Moreover, some of the link roads inside the project will be extended for better connectivity, and sidewalks will also be built along the lake. Recreational facilities will be developed at different spots in adjoining areas of the lake. Driveways, footpaths, walkways and viewing decks are also planned.

Rajuk officials said the High Court in May 2006 directed the authorities to stop illegal grabbers from filling up the Gulshan Lake. Later in an order in 2009 the High Court also asked Rajuk to restore the original lake by evicting the grabbers.

In April 2012 the HC directed the government to demolish in 15 days all the buildings erected by illegally encroaching on Gulshan Lake.