Padma bridge approach roads

The government has appointed the army and Bangladesh University of Engineering and Technology (Buet) for supervising the construction and security of the Janjira and Mawa approach roads of the proposed Padma bridge.

“We have approved the Bangladesh Bridge Authority’s proposal for appointing the army and Buetto supervise the construction and security of the approach roads of the proposed Padma bridge at the cabinet committee on public purchase,”Finance Minister AMA Muhith told journalists Sunday after a meeting of the committee.

He said the government wouldalso appoint three foreign consultants for the construction of thebridge, whichwould start in January next year.

As per the Bridge Authority’s proposal, the Bureau of Research, Testing and Consultancy of Buet will supervise, alongside the army, the construction of the Janjira and Mawa approach roads to the Padma bridge.

Bridges Division Secretary KhandokerAnwarul Islamearlier said they had decided to involve the Buet wing in the supervision work as the army did not have the full capacity of carrying out different supervision work, including checking the design of the approach roads.

Officials concerned said there had also been a directive from the prime minister on giving the “priority” project to Bangladesh Army and Buet jointly.

The cost of the approach road work has been estimated at Tk728.3m while the total cost of the project, including appointment of the army and Buet, will stand at Tk1.335bn, according to the proposal.

The communication ministry floated international tender for the construction of the main Padma bridge on June 26 and the last date for its submission expired one week ago. Three firms have so far submitted proposals.

However, the deadline for submitting tender proposals has been extended by eight weeks ending November 3.