Earth-filling work now goes to Diesel Plant: Rampal Power Project

As PDB could not complete even 1% of the work in 15 months, the government now plans to assign Bangladesh Diesel Plant Ltd to accomplish the earth-filling of the country’s first coal-fired power plant proposed at Rampal in Bagerhat district.

Earlier, the Power Development Board was assigned to fill up 420 acres of land with sand in 18 months. But the PDB could accomplish less than 1% of the work in 15 months.

The sources in the power, energy and mineral resources ministry said till the last month, only 0.57% of the land-filling work had been completed.

The 1320-megawatt power plant will require a 420-acre land which should be 5.5 metres high. The land needs to be filled with 9.1m cubic metres of sand.

If the work is given to Bangladesh Diesel Plant Ltd is signed, the government will need to spend Tk141 for a cubic metre of sand-filling. The total cost of the land-filling may stand at Tk1.27bn.

Bangladesh’s state-owned PDB and India’s state-run National Thermal Power Corporation (NTPC) is implementing the Rampal plant under a joint-venture deal which was signed in January 2012. The plant will have two units of 660MW each.

Facing different difficulties, the both sides reset the time to complete implementation of the plant by 2016 instead of the earlier 2014.

But during the signing of the deal, the two parties promised an immediate start of works to bring the proposed plant into operation in late 2013 or early 2014.

As the project site is near Sundarbans, environment campaigners of the both countries raised voice against power plant in the area which can be a threatening to biodiversity of the world’s largest mangrove forests.

According to sources at the local land office, the government already acquired around 1834 acres of land at Sapmari Katakhali and Koigardaskathi mouza in Rampal upazila. The land was handed over to the Power Division.

A number of about 1,400 land owners were paid Tk624.5m in compensation since October, 2011.

The opposition BNP also protested the joint venture power plant and termed the deal as “anti-State” and “bad” for the area’s ecological system.