Non-wage cost projects riddled with irregularities

Under the non-wage cost project, a culvert was supposed to be constructed in front of Prabir Dhali’s house at Kamarkhola union under Dacop upazila in Khulna. Necessary materials were also bought in that regard.

But even after a year the culvert has still not been constructed and the materials kept in the open had begun to decay.

Despite spending the money, the project could not be implemented adding woes to people’s sufferings. Locals alleged that the former project manager embezzled the money from the project.

Md Nur Islam Gazi of Kamarkhola said Tk2 lakh 15,000 was allocated to build the culvert.

He alleged that many such works under the non-wage cost project in the area had not been implemented. A bridge at Pankhali, culvert in Laudob and another culvert at Sutarkhali are facing the same fate. Former project manager of Dacop upazila Md Selim Khan said he was transferred eight months ago and was now working in Ashashuni.

“Sometimes projects are delayed because local parliament members place late proposals and budgets. Then there is the monsoon. But this does not mean corruption.”

According to the district relief and rehabilitation office, non-wage cost projects are meant to benefit the extreme poor by providing them employment in local infrastructure development projects.

For Dacop upazila, a total of about Tk55 lakh was allotted in 2013-2014 fiscal year to implement 112 projects. According to the report submitted to the ministry, these projects had been shown as fully implemented.

Under these projects rural infrastructure like roads repair, box-culvert construction, building embankments and developing other public places are done.

Overseen by the relief and rehabilitation ministry, these projects have pre-registered workers who get Tk200 each.

In 2013-2014 fiscal, 3082 workers were paid Tk2 crore 46 lakh 56,000 and in the second phase 3085 persons received a total of Tk2 crore 46 lakh 80,000. Satyajit Kumar Roy, chairman of Laudob union parisahd said the project to build a culvert in his area had not been finished in last one year.

“We do not know the current situation of the project. When the previous project manager was transferred, he did not handover the work properly to anyone.”

UP Chairman Sudeb Roy of Banishanta alleged that most of the construction materials used in the projects were of low quality.

“The former project manager Md Selim embezzled lots of money by not finishing the project and also using low quality materials.”

Reiterating the claims of others, Sutarkhali union member Aboni Baidya said the big culvert on the canal at 2no ward had also not been built.

Sources at district relief and rehabilitation office said in nine upazilas of Khulna, about Tk1 crore 32 lakh 3,025 was allocated in the first phase for 334 non-wage cost projects. The amount was Tk1 crore 32 lakh 15,607 was set aside for the second phase.

Though the report to the ministry claimed hundred percent implementation of these projects, locals claimed many works were left unfinished.