Over two years into the project, the design for Bus Rapid Transit is yet to be finalised.
The project authority had fixed February 2015 as the deadline for completing detailed design of the bus lanes from Airport to Gazipur that would be used for the bus-based mass transit.
But the failure means that the project, which began in end 2012, will be delayed further.
However, the project authority has floated a tender for the BRT Gazipur depot recently.
BRT project director Afil Uddin told the Dhaka Tribune: “Although there is no detailed design, the tender floated for the Gazipur depot will not create any problems. We want to proceed quickly as two years have already passed without any visible progress.”
Earlier, Road Transport and Bridges Minister Obaidul Quader said: “The BRT project came across various problems. Hopefully, within June the final design will be complete. After that the tender for construction of BRT will be floated and work will begin by the year end.”
The BRT project is expected to improve connectivity along the Dhaka-Gazipur route. It is estimated that 140 buses will carry 40,000 passengers per hour. The new project hopes to cut down commuting time significantly. A trip from the airport to Joydebpur is expected to take 40 minutes at most once the mass rapid transit becomes operational.
The project is expected to cost about Tk2,040 crore. The Asian Development Bank, French Agency for Development – AFD, Global Environment Facility will fund Tk1,650.7 crore and the rest will be funded by Bangladesh government.
November 2017 is now the new deadline and operations will begin from December the same year. However, the completion date had been fixed for December 2016 at the beginning.
The project consists of 20km BRT corridor, six flyovers, four kilometres of elevated roads, 141 connecting roads, 12km of storm drains, eight-lane Tongi bridge, Gazipur bus depot, Joydebpur and Airport bus terminals. The six flyovers would be constructed at the airport crossing, Jasimuddin Road in Uttara, Konia, Boardbazar, Vogra, and Joydebpur in Gazipur.
The BRT project is being implemented by Roads and Highways Department, Bridge Authority, and Local Government Engineering Department.
According to the authorities, land acquisition for the project will be complete by the end of this year. A project official said the government has already completed the field survey, finalised the preliminary design, and also finalised the operational plan.
The fully state owned Dhaka Bus Rapid Transit Company Limited will run the rapid transit operations.