Usually, development projects move fast at this time of the year as whether remains dry, but this year, implementation of mega structures has slowed down considerably, mainly because of the ongoing political unrest in the country.
Several government agencies – mainly attached to the communication sector – has projected and proposed spending cuts in the upcoming revised Annual Development Programme (ADP), due in a few months. The agencies include the Bridges Division and the railway – two of the biggest development spenders in the country.
Sluggish execution of development projects has prompted the Planning Ministry to slash annual foreign aid spending targets as well.
Officials from the Bridges Division – implementation agency of the country’s biggest ever development project Padma bridge – said they will not be able to spend Tk235 crore of the budget allocated for them, fearing transportation and security problems due to the ongoing unrest.
They said they are now going to quote Tk7,865 crore in the revised ADP instead of the Tk8,100 crore allocated in the development budget for the current fiscal year. The original amount was the highest allocation in a development project for the 2014-15 fiscal.
An official told the Dhaka Tribune yesterday: “We do not need the entire fund this fiscal year as expenditure has been very slow because of political violence.”
Sources said, the Bangladesh Bridges Authority spent about Tk2,500 crore for the Padma bridge out of a total disbursement of Tk3,225 crore until January 20.
The China-based contractor of the Dhaka-Chittagong highway up-gradation project has recently wrote to the Home Ministry expressing concerns about security amid the ongoing unrest.
China’s state-owned construction and engineering company Sinohydro – currently implementing the project for upgrading the Dhaka-Chittagong Highway into four lanes – sent the letter after some of its materials-laden trucks and vehicles got attacked and burned by arsonists at various places.
The similar up-gradation project of the Dhaka-Mymensingh Highway has also been facing difficulties because of the unrest.
Implementation of the metro rail project in Dhaka city and the works for repairing old roads and building new ones across the country have also been facing a lot of trouble because of blockade-related atrocities.
The Bangladesh Railway has also decided to slash its development budget by nearly Tk925 crore for the upcoming revised ADP. In the main ADP for the ongoing fiscal year, railway got Tk4,526 crore for implementing 41 projects.
“The [railway] ministry will require only about Tk3,600 crore to execute the projects. Nearly one thousand crore may remain unspent as the transportation of essential construction materials have been very slow because of hartal and blockade,” an official from the Railway Ministry told the Dhaka Tribune.
Over the last five to six years, the government has significantly increased investment for improving the railway sector.
Because of indiscriminate arson on vehicles on highways in the ongoing blockade that enters day 25 today, the country’s general transport sector has come to a standstill. Costs are going through the roofs, but more alarmingly, owners are not ready to send their vehicles on the long route at all.
During months of political unrest before the January 5 general elections last year, transportation costs have increased by up to five to 10 times. This year too, the costs are fast pushing up towards that level.
As of January 20, the implementing agency has spent Tk284 crore out of a total of Tk500 crore of budgetary allocation for the Dhaka-Chittagong highway up-gradation project. As for the Dhaka-Mymensingh highway project, around Tk178 crore has so far been spent from the original allocation of Tk398 crore.
As for foreign aid disbursement, slow execution of development projects has forced the government to slash annual foreign aid target by $360 million, Planning Ministry sources said.
“We have been forced to reduce the aid target as the government agencies have shown weak performance in project execution. Despite several measures, no improvement in project implementation is being observed,” an official said.
He added: “When agencies fail to implement foreign loan or grant-supported projects, external assistance disbursement by donors automatically decreases.”
During the first half of the current fiscal year, public agencies spent Tk22,494 crore, accounting for only 28% of the Tk80,315 crore ADP. Only about 27% of the total foreign aid allocation in the current ADP could so far be spent.
Firoz Ikbal, chief engineer of the Roads and Highways department, told the Dhaka Tribune yesterday: “Our local offices remain very busy at this time of the year because most development funds are released from December to February. But because of arson and vandalism on the highways, equipment such as excavators cannot reach project sites. That is significantly slowing down the works.”
However, Road Transport and Bridges Minister Obaidul Quader rejected any trouble on the highways.
“The construction works of roads and bridges are going on smoothly. Mega projects are moving ahead fast. The Dhaka-Chittagong four-lane project has faced some troubles because of the blockade, but that problem has already been solved,” he claimed.
The minister also said: “As for the Padma bridge and the Joydebpur-Mymensingh highway four-lane projects, because the army is involved, blockade supporters have not been able to create much trouble.”