While the government hopes to inaugurate the much-awaited Padma Multipurpose Bridge by 2018, it is yet to construct a railway from Dhaka to Faridpur that would connect to the bridge.
The word “multipurpose” in its name refers to the road and railway link it is supposed to offer across the Padma River. An Australian firm has completed a feasibility study of the railway on the bridge but if tracks are not laid from Dhaka to Faridpur, the tracks on the bridge will be of no use.
Director General of Bangladesh Railway, Taffazzal Hussain said: “We are seeking funds for the construction of a railway track to connect Dhaka to Faridpur via the Padma Bridge.”
“We have sent a letter to the Asian Development Bank but they have not replied yet. In the meantime, the Planning Commission will try to collect funds for the Dhaka-Faridpur rail line,” he said.
A visit to the Padma Bridge project site on December 17 found construction work in full swing. Soil testing, dredging and river training work seemed to be moving quickly.
But there was no work being done, anywhere between Dhaka and Mawa, to build a railway track.
In January 2011, the Executive Committee of the National Economic Council (Ecnec) passed the design of the Padma Bridge that included rail tracks on the bridge.
Railway sources said the Railway Ministry recently completed the Detailed Project Plan (DPP), according to which the Dhaka-Faridpur rail track will fall under two projects: one from Kamalapur Railway Station in the capital to Mawa and the other from Jajira Point to Bhanga upazila in Faridpur district.
The Padma Bridge railway track falls under the first project.
Sources said the draft DPP had been submitted to the Planning Commission for review.
The total cost of the two projects is estimated at Tk13,200cr. Authorities calculate that around Tk5,000cr would be needed for land acquisition and resettlement while the rest, about Tk8,200cr, will be needed for the construction of the rail track, rail bridge, stations and related infrastructure.
Sources said it would take 82.32 km of rail track to run a train on the Padma Bridge – 44.32 km to connect Dhaka to the bridge, 6.15km to span the bridge, and 31.85 km from the bridge to Bhanga.
Railway Ministry sources said they hope the rail link will be in operation by 2022.
But it all depends on raising the funds by the beginning of the coming year.
The bridge’s rail link will not likely be ready if the bridge opens on time in 2018, sources said.
But Railway Minister Mujibul Haque said: “If the construction work starts quickly, it will be finished by 2018.”
Speaking to the Dhaka Tribune yesterday he said: “The prime minister has directed us to start the construction of the Dhaka-Faridpur railway. We hope the construction of the Dhaka-Faridpur rail route via the Padma Bridge will be started in the shortest possible time.”
“We hope the ADB will help fund the rail link. But they have not responded yet,” he said.
The feasibility study estimates that more than 365.10 hectares of land must be acquired for the railway, of which 273 hectares are private land. Moreover, 92 hectares are Roads and Highways land.
The project envisions four large bridges including over the Buriganga River and Shitalakhya River and 56 rail bridges of different lengths. Five level crossings and 3 flyovers will need to be built where the railway intersects the national highways.
The proposed railway spans 87 moujas, including those of Dhaka City Corporation and several upazilas. A very large number of establishments have to be removed from the alignment – a huge task, according to railway sources.