The government monitoring committee on six fast-track projects has expressed its satisfaction on the progress of the large-scale projects including the construction of the Padma bridge.
Following a meeting yesterday at the Prime Minister’s Office (PMO) to review the projects’ implementation, the PM’s Principal Secretary Abdus Sobhan Sikder told the Dhaka Tribune that a total of 35% progress have been made in all the six fast-track projects.
The six projects worth $15.5bn include the Padma bridge project, deep seaport, metro rail, 1,320MW Rampal Power Plant, 1,000MW Rooppur Nuclear Power Plant and the LNG terminal project.
Speaking on the Padma Multipurpose Bridge project, he said the committee was “satisfied” with the process of implementation for its construction.
He also mentioned that China Major Bridge Engineering, the company that was awarded the main job of constructing the bridge, has already brought heavy machinery to the Chittagong port and was planning on bringing the machines to the bridge site before floodwater recedes.
He added that there was no bar to implementing the metro rail project as disputes between Rajdhani Unnayan Kartripakkhya (Rajuk) and the metro rail authority had been solved. Compensation would be paid by this week to the people whose land was acquired for the metro rail project, the premier’s principal secretary said.
The implementation of all the six fast-track projects were within the time frame of the project durations, Sikder said.
The committee also noted progress in the construction of the Rampal Power Plant as its main boundary wall had already been constructed and a power plant terminal had also been built at the project site, he added.
Sikder said the next meeting of the monitoring committee would be held at the PMO next month and be presided over by Prime Minister Sheikh Hasina.
Although the main work of the much-talked about Padma Bridge was yet to kick off, the government recently decided to award the river training work to Sinohydro Corporation, a Chinese Company.
There has also been reportedly little progress in the deep seaport and metro rail projects as the government was yet to decide on the source of funding for the two projects.