Bashundhara gets dredging work for 24 water routes

The cabinet committee on public purchase has allowed Bashundhara Dredging Company Ltd to dredge 24 water routes in the country’s southern part.

It has also approved increasing the construction cost of a bank-protection yard at the Janzira point of the proposed Padma bridge by 9.17% – caused due to delay by the Indian construction firm.

The committee yesterday approved the proposals with Finance Minister AMA Muhith in the chair.

The meeting gave the go ahead to a shipping ministry proposal for dredging the Barisal-Jhalakathi-Barguna-Patharghata water route under the revised Capital Dredging of River System in Bangladesh project.

The shipping ministry submitted the proposal of the Bangladesh Inland Water Transport Corporation in October last year. But the committee rejected the proposal and sought clarifications on five points, including whether the national competitive bidding process had been followed.

According to the ministry, an advertisement for tender was placed in newspapers and posted on the BIWTC website for some time under the Public Procurement Regulation to make the bidding more competitive.

Bashundhara was selected as the responsive firm which quoted Tk96.26 crore for dredging 38 lakh cubic metres.

Regarding bank protection at the Janzira point, a senior official of the Bridges Division told the meeting: “We will extend the deadline for the Indian firm Bhartia-MBEL (JV) Ltd to build the 2,163km river bank protection yard. Thus, we can save the time needed in case we floated tender again.” As per the initial contract, the cost of building the Janzira point yard was Tk135.97 crore.

However, the Bhartia-MBEL failed to bring in all the necessary heavy equipment during the rainy season and the Bangladesh government has still not been able to manage to convince a private owner to give up its land for the bridge; as a result, the construction of the yard will now cost the government an extra Tk12.47 crore.