Alleged irregularities and corruption had been delaying the re-excavation of Valukshi-Baradulari canal under Gournadi upazila of Barisal.
After visiting the spot, it was learnt that the re-excavation of 7km long portion of the canal from Khan Bari of Baradulari to Valukshi Bazar, connecting Palardi River at the cost of Tk42 lakh started from January 1, 2013 and was scheduled to be completed by December 31, 2013.
World Food and Agriculture Organization funded the re-excavation project to increase food production by extending irrigation facilities under a specified design and schedule, said Moti Lal Roy, sub-assistant engineer of Bangladesh Agriculture Development Corporation, Gournadi office.
Local IRRI-Boro block managers and farmers said labours of the contractor only re-excavated 2-3 feet deep earths and deposited those on the slopes – inside the canal, causing re-siltation that is hampering free water flow.
On other hand, in collaboration with the BADC authorities the contractor of the project had been using two 5qeusec electric pumps and one 2quesec electric pump to supply water in the canal for water irrigation in 17 IRRI blocks.
Different block managers and farmers of the area alleged that the authorities had been supplying water to the canal before completing the re-excavation to erase the evidences of the irregularities and corruption in the project.
As the depth and width of the canal were not fixed before starting the project, the work would not give any satisfactory result for the farmers in developing production, they added.
AKM Abdul Hye, executive engineer of BADC Barisal office, said the contractor had completed 3.68km out of 7km work within December 31, 2013.
Md Faruk Mia, owner of Faruk and Brothers, contractor of the project, had denied the allegations.