Elevated expressway project cost goes up

The Bridges Division has decided to appoint a Thailand, UK and Netherlands joint venture firm as an independent engineer for the construction of the first Dhaka elevated expressway project under public private partnership (PPP).

The project, aimed at easing the perennial traffic gridlock in the city, was laid out over five years. But for the last one-and-half years, since its inauguration by Prime Minister Sheikh Hasina in April 2011, the construction work of Bangladesh’s first big PPP project was mostly stalled. Now the project has only three-and-half years left.

Now the project appears to be gearing up as a new proposal from the Bridges Division in this regard will be placed at the next meeting of the cabinet committee on economic affairs for approval.

The joint venture firm is Thai Mott MacDonald Ltd (Thailand) - Mott MacDonald Ltd (UK) – Euroconsult Mott MacDonald BV.

The proposal of revised alignment of the Dhaka elevated expressway will also be placed for approval in the same cabinet committee meeting. This revision will increase the estimated project cost by Tk2.37bn or 2.72% from the previous Tk87.03bn and viability gap financing will also be increased to Tk24.13bn.

Bridges Division Secretary Khandaker Anwarul Islam told the Dhaka Tribune on Monday the selection of an independent engineer and revised alignment for Dhaka elevated expressway was under process.

“But we do not know the actual date for starting the project yet. We hope that the work will begin within the tenure of this government,” he added.

According to the Bridges Division proposal, due to the complexity of acquiring land for the elevated expressway project in Dhaka city, the appointment of an independent engineer was delayed. The cost of appointment of an independent engineer will be Tk528m. Two other foreign firms also participated in the tender process: High Point Rendel UK and South Korean firm SUNJIN Engineering and Architectural Company.

The other proposal says the new alignment will increase the length of Dhaka elevated expressway to 40 kilometres. In the first phase an eight kilometre route from Shahjalal International Airport to Tejgaon will be built, and an eight-kilometre route from Tejgaon to Kamalapur and a seven-kilometre from Kamalapur to Kutubkhali of Shanir Akhra will be built in the second and third phases.

Landing and climbing ramps of the road will take up the remaining 17km.

The alignment of the expressway was approved at a cabinet meeting on August 23, 2010. The alignment had included Shahjalal International Airport-Kuril-Bannani-Mohakhali-Tejgaon-Moghbazar rail crossing corridor and the Khilgaon-Kamalapur-Golapbagh-Dhaka-Chittagong road.

As per a concession agreement, the Thailand-based contractor Ital-Thai would build the Tk87.03bn elevated road, of which the government would bear Tk22.58bn on the basis of Public Private Partnership. The government had inked the deal with the firm in January 2011, when the then communications ministry said construction would be complete by the middle of 2014.