Production at the country’s lone coalfield at Barapukuria, Dinajpur remained suspended on Friday as the contractual miners continued their indefinite strike for the second day to drive home their five-point demands that include safety and security issues.  

“The miners, mostly from XMC, the mine’s contractor company, abstained from work at around 6pm on Thursday suspending production,” General Secretary of Barapukuria Workers-Employees Union Shafiqul Islam told the Dhaka Tribune yesterday. Chinese company XMC with another consortium, led by China National Import and Export Corporation (CMC), has been producing coal from the mine since 2005.

Out of 1,041, around 250 miners continued their demonstration in front of the main gates of the mine. Citing mining as being a risky and often life-threatening job, Shafiqul said that they sought security for the miners through regularisation of their jobs and life insurance. Other demands include disbursement of bonus profits for 2011 and 2012, introduction of a rationing system and the appointment of Bangladeshi doctors to ensure their proper treatment.

During the last five years, miners staged several such agitation programmes, including work stoppages, to demand regularisation of jobs so that they could enjoy benefits like insurance, Shafiqul said. “Every time we rallied to realise our demands, the mining authorities assured us of meeting those demands. But they never kept their promises,” he claimed.

Earlier, in a memorandum submitted to the Barapukuria Coal Mining Company Ltd (BCMCL) managing director, the workers threatened to go out on strike unless their demands were met by Wednesday. “The agitating workers alleged that they would continue the demonstration for an indefinite period of time until their demands are met as the authorities did not fulfil the promises they repeatedly made.” Shafiqul said.

Md Aminuzzaman, MD of BCMCL said they were trying to resolve the problem through discussion. He, however, alleged that the workers reached an agreement that they would not go for a strike but suddenly enforced one, halting production. 

The Power Development Board (PDB) procures 80% of the coal for use at the only coal-fired power plant near the mine. The 250MW plant, now producing 120MW of electricity, needs around 2,500 tonnes of coal on a daily basis. Some steel mills and heavy industries, and brickfields also procure coal from the BCMCL.