The fast-track projects, which are considered very important to accelerate economic growth, have turned into slow-track ones as work progress has been slower than expected.
According to the minutes of the latest meeting of the high-profile committee on fast-track projects, all the projects except the Padma bridge construction are progressing at a snail’s pace.
These projects were launched nearly two years ago.
The six top priority projects involving Tk157,000 crore were placed under a Fast-Track Project Monitoring Committee headed by Prime Minister Sheikh Hasina. The government later included Payra Dwip seaport in its top priority list.
However, the implementation cost of these fast projects will cross Tk257,000 crore due to the delay in implementation, the Finance Ministry estimates.
In January last year, the government identified the projects as utmost important ones to boost economy.
It targeted to set up a liquefied natural gas terminal in two years, the Padma bridge in three years, Rooppur Nuclear Power Plant in two years, Rampal Thermal Power Plant in eight years, Dhaka Mass Rapid Transit Development (metro rail) in eight years, and Matarbari coal-fired power plant in eight years.
Of the six projects, some 13.5% work of the main part of the Padma bridge has been completed while 48.5% of Jazeera and 50% of Mawa connecting roads were completed in time. The initial cost of the project was estimated at Tk20,507 crore, but the cost has already increased to Tk28,793 crore.
Meanwhile, the Rooppur Nuclear Power Plant has made no headway as the final agreement is yet to be signed with the Atomstroy Export of the Russian State Atomic Energy Commission, which is implementing the project.
Similarly, the metro rail project is also lagging behind the schedule. The project was divided into eight packages for execution on time; tenders have been floated for six of the packages so far.
The basic design for the metro rail has been completed and at this moment topographic and other surveys are going on.
The construction of the LNG terminal has also faced the same fate as the term sheet agreement between Petrobangla and Excelerate Energy Limited has been signed, and metrological ocean study has been completed. Tender has been floated seeking applications for carrying out the primary task of the project.
For the Rampal power station, also known as the Maitree Super Thermal Power Station, around 1,834 acres of land on the bank of the Poshur River, close to the Sundarbans, have been selected. Land-filling is on in some parts of the project area.
For the Matarbari 1200MW ultra super critical coal fire plant, 1,500 acres of land have already been acquired and a consultant for the project has been appointed.
The process for appointing a contractor for the project is only in the first phase.
The detailed project proposal for the Payra Dwip seaport, which was included in the priority list later, has been sent
to the Planning Commission, and a meeting of the project evaluation committee has been held.
Earlier, Principal Secretary at the Prime Minister’s Office Abul Kalam Azad said the government wants to complete the projects within stipulated times.