Ecnec okays second submarine cable project

Bangladesh is on its way to be connected to a second submarine communication cable by June next year, following a government approval for a Tk660 crore project to ensure uninterrupted voice and data transmissions with the rest of the world.

The new connection with the 20,000km-long SEA-ME-WE-5 submarine cable, which stretches from Singapore to the Middle East to Western Europe and connects 17 countries, will provide high speed uninterrupted internet services at a cheaper cost than the first cable.

The project titled “Regional Submarine Telecommunication Project, Bangladesh” was approved yesterday at a meeting of the Executive Committee of the National Economic Council (Ecnec), chaired by Prime Minister Sheikh Hasina, at the capital’s NEC conference room.

Out of the total project cost, the government would provide Tk166 crore, the Islamic Development Bank Tk352 crore as project assistance, and Tk142.64 crore from the funds of the public agencies concerned, Planning Minister AHM Mustafa Kamal told reporters after the meeting.

Bangladesh Submarine Cable Company Limited (BSCCL) will implement the project by June 2016.

In 2006, the country got connected to its first submarine cable SEA-ME-WE-4 (South East Asia- Middle East-West Asia).

Planning Commission Member Arastoo Khan said that once the new link is established, the country would receive an additional 1,300Gbps (billions of bits per second) bandwidth, which is many times greater than the first submarine cable connection.

The data transmission capacity of the new cable will gradually be increased up to 24 terabits per second (Tbps), he said.

At present, the BSCCL has 200Gbps bandwidth and the government has allowed it to export half of the bandwidth.

“With the arrival of the new connection, it will provide us standard and uninterrupted international voice and internet services at a low cost. It will also help increase the bandwidth to keep pace with the increasing demand for bandwidth,” Arastoo added.

The site for the landing station of the second undersea cable has been selected at Kuakata under Patuakhali’s Kolapara upazila.

The Cox’s Bazar landing station for the first submarine cable – upon which the country’s internet mainly depends – suffers frequent outages, each time requiring over a week to restore the system.

Once the new project is implemented, it would help introduce internet services to the doorsteps of the people in rural areas and increase data storage through the additional landing station connection, said the planning minister.

The submarine cable project was one of the 10 projects worth Tk2,365.34 crore that received approval from the Ecnec yesterday.