The tender was floated on August 23 while the last date for submission of it is October 10, said Habib Uddin Ahmed, general manager (Mine Operation) of the BCMCL.
Talking to the Dhaka Tribune yesterday, the BCMCL official said: “The authorities have floated the global tender as the present agreement with a Chinese consortium will expire by August, 2017.”
On December 10, 2011, the BCMCL signed a deal with the Chinese company XMC, together with another consortium led by China National Import and Export Corporation (CMC), at a value of $200.98 million to extract 5.5 million tonnes of coal from the second slice by August 10, 2017.
“The coal extraction work was suspended between March 31-May 23, 2014 because of equipment transfer procedure from 1212 to 1208 face while the production was suspended in between July and November, 2014 as water started coming out of 1205 face,” Habib Uddin added.
“As a result, the total production of coal during the last four production years stood at about 3.3 million tonnes which amounts to 6.25% short of the given target of 3.6 million tonnes,” he further said. “But, we hope that we will be able to extract 5.5 million tonnes of coal by August 2017 from the mine.”
“We have adopted the Long Wall Top Coal Caving (LTCC) method for extracting coal from the mine on May 8, 2013, upgrading the Long Wall Mining system and the current method is considered ideal for thick seams.”
“Productivity has been enhanced to a notable extent after the introduction of the LTCC method. In addition, it has allowed up to 80% recovery of additional coal,” he added.
The PDB is the biggest consumer of the coal extracted from the mine. It procures 80% of the coal for using in the power plants near the mine, he added.
The mine has an estimated reserve of about 390 million tonnes, stretching over a 6.68 sq-km area, according to a 1985 study of the Geological Survey of Bangladesh.