Railway minister: Train operation on Padma Bridge from next June

Railways Minister Nurul Islam Sujan has said that rail traffic will start on the Dhaka-Bhanga route through the Padma Bridge in June 2023.

He made the remark while inaugurating the installation of the railway track on the Padma Bridge’s Zajira point on Saturday.

The minister also said that there is a 28km railway line from Bhanga to Zajira. 

“The work of laying the railtrack on this road will be completed within the next month,” he added.

Sujan also mentioned: “Bhanga station is being developed into a modern junction. Magura, Gopalganj, and Faridpur rail connection will be the station point at this junction.”

The minister said: “So far, 66% of the project’s Dhaka-Mawa part, 85% of Mawa-Bhanga and 52% of Bhanga-Jessore sections are completed.”

In addition, 68% of the financial progress of the project has been made while 70% of the physical work has been completed, he told reporters.

Army Chief Coordinator of Railway Project Md Zahid Hossain, various army officers, railway construction officials, Upazila Assistant Commissioner (Land) Mahmudul Hasan, Bhanga Thana police officer Md Ziarul Islam, among others, were also present.

On June 15, the minister said the Padma Bridge Rail Link Project is one of the ten top-priority projects of the government.

The project has been divided into three parts for timely implementation.

The cost of the 169km railway track from Dhaka to Jessore is around Tk39,247 crore.