Loadshedding continued across the country on Tuesday as consumers in many areas in the capital Dhaka and elsewhere experienced power cuts for several hours in a number of spells.
According to the Bangladesh Power Development Board (BPDB), the country had to experience about 1,400MW of loadshedding as it generated less than 13,000MW against a demand of over 14,000MW.
As a result, consumers in and outside the capital had to experience frequent interruption and loadshedding, said an official of the BPDB.
He attributed the fall in power generation to the shortage of gas supply to the power plants, saying that the BPDB had to hold up generation of about 3,400MW of electricity despite having the capacity.
Dhaka city alone had to experience over 500MW of loadshedding.
Dhaka Power Distribution Company (DPDC) Managing Director Bikash Dewan said his areas had to go for 400MW of loadshedding to cover the gap between demand and supply.
“DPDC received 1,200MW of electricity against the demand for 1,600MW”, he told UNB.
He said he is trying to make a plan for loadshedding so that people could be aware of the interruption to mentally accept the power cut.
“If we can implement the plan, it will give lesser sufferings to the people”, he said.
The areas under DPDC in the city include Mohammadpur, Dhanmondi, Lalbagh, Sutrapur, Jatrabari, Malibagh, Mogbazar, Tejgaon, Kakrail, Santinagar, Agargaon, Kalabagan, Kawranbazar and Tejturibazar.
The areas under Dhaka Electric Supply Company Limited (Desco) also had to experience black outs in several spells.
Desco had to resort to loadshedding of 134MW in its areas, said its Managing Director Kawsar Ameer Ali.
He said Desco was allocated 800MW plus electricity against a demand of over 1,000MW.
Desco mainly distributes electricity to the city’s west, northwest, and eastern parts, which include Uttara, Mirpur, Badda, Gulshan, Banani, Baridhara, Niketon, and Badda.
People outside the capital also complained that they had to experience blackouts for several hours.
“Consumers in many areas had to stay without electricity for 5-6 hours a day in different spells,” said an official of the Consumers Association of Bangladesh (CAB), which received reports from different areas across the country.
Meanwhile, the Ministry of Power, Energy and Mineral Resources held a high-level meeting with officials of BPDB and Petrobangla to find a way to improve the power and gas supply situation.
An official who attended the meeting said Petrobangla was asked in the meeting to increase gas production so that more gas-fired power plants can resume operation.