PM Hasina to inaugurate Padma Bridge on June 25

Prime Minister Sheikh Hasina will formally inaugurate the much-awaited Padma Bridge on June 25.

Road Transport and Bridges Minister Obaidul Quader made informed the media following a meeting with Prime Minister Sheikh Hasina at Ganabhaban on Tuesday

The prime minister decided that the name of the bridge will be Padma Bridge, Quader said.

Meanwhile, the Bangladesh Bridge Authority (BBA) has already formed 18 preparatory committees and sub-committees to celebrate the completion of the mega project.

Commemorative stamps and inaugural envelopes will be issued ahead of the occasion.

According to officials, the construction of the main bridge will be completed by May as 98% of work on it has already been done. However, the overall progress of the project is 93.5% since work on river training has been delayed.

Officials concerned say now it is possible for vehicles to be driven across the bridge.


Also Read



The work of carpeting on the bridge has been completed. Except for railing and road markings on the bridge, all the other works have already been completed.

The installation of the railing on the bridge will also be done before the inauguration.

However, 12.3km railings will be installed gradually on both sides of the 6.15km-long-bridge on three-foot-high walls. The power sub-station edifice will be completed by next year.

Besides, river training work will continue for another year. About 9% of the river training work under the project is still incomplete.

The construction of the bridge began in November 2015 with the aim of connecting the country’s south-western region with the capital via road and rail.

The project cost rose to Tk30,193 crore in 2021 after several revisions. Rail tracks will be set up on the lower deck of the two-storey Padma Bridge at a cost of some Tk40,000 crore.

The Dhaka-Mawa-Bhanga Expressway leading to the bridge has been constructed at Tk11,000 crore.

To develop connectivity with the road and rail network to the south-western regions of the country, the government’s expenditure is over Tk80,000 crore to date.