Tk370cr down the drain as government closes Khulna gas project
Publish : 26 Dec 2016, 02:09
With Tk370 crore spent and piles of purchased pipelines and equipment sitting in stack yards, authorities have no good answer as to how the incurred costs will be recuperated.
The ambitious South-West Gas Distribution Network Project began seven years ago with the aim of bolstering a dwindling gas reserve in the southwestern region. The plan was to build an 845km pipe line network to distribute gas to five southwestern districts – Kushtia, Jhenaidah, Jessore, Khulna and Bagerhat – along with Mongla. The project was approved in 2010.
A revised budget of Tk600 crore was approved on June 12, 2013, financed by an Asian Development Bank (ADB) loan of Tk285 crore and Tk315 crore from the government exchequer.
Now, with the shutdown of the project work, the consumers in Khulna are not going to get new gas connections – something for which the people of Khulna have fought for long.
State-owned Sundarban Gas Company Limited, the project implementation agency, says that as per a government decision they have submitted a letter to Petrobangla for closing the project.
Petrobangla has passed down its recommendations to the Energy and Mineral Resources Division (EMRD) and EMRD to Planning Division.
The Planning Ministry will officially close down the project.
In these seven years, around 95% of the pipelines and various other equipment and fittings needed for the project have been procured through international tender.
Line pipe, tape and primer, thermoelectric generator, cathodic protection materials and seamless pipe have been purchased and preserved in different stack yards.
A programme was undertaken to develop the working efficiency of Sundarban Gas personnel, under this project. But it was postponed.
Sundarban Gas acquired 65 decimals of land in Khulna to build its head office under the project. Land acquisition for the pipelines had also been completed in three districts.
Project Director SM Rezaul Islam said that a total of Tk370 crore has already been spent for different purposes of the project. Of that, Tk242 crore was taken from the ADB and the rest Tk128 crore came from the government exchequer.
When asked how the ADB loan was going to be repaid, Rezaul said: “The project started as per the government's decision. So, the government will make further decisions in this regard.”
Sundarban Gas MD Md Khalequzzaman said a circular has already been issued for the sale of the pipes and other equipment bought for the project to other state-owned companies under Petrobangla and will be sold through negotiation, he added.Why did this happen?Md Zakir Hossain, chairman of Sundarban Gas and additional secretary of EMRD, said as the gas reserves were on the wane, the government did not feel the need to implement this project anymore.
Asked why the decision of closing down the project was made after seven years, Zakir, who is also working as an acting chairman of Petrobangla, replied that the government had previously thought it was necessary but now it does not.
According to energy expert Dhaka University Professor Dr Badrul Imam, this was an unsatisfactory answer.
“When the issue of the dwindling gas reserve came to limelight as early as 2005, why would this sort of a project be taken up in 2010?” he asked.
He believed that the failure of this project was an example of how this country lacked proper planning and policy in the energy sector.
Dr Badrul suspects that a group of officials had coaxed the government into undertaking this futile project for their own benefits.
“I think the government should take a lesson from this,” he warned.No gas for Khulna yetWith the scrapping of this project, Khulna division residents' hopes of having gas supplied to their doorsteps comes to a halt.
Brihattara Khulna Unnayan Sangram Somonnoy Committee President Sheikh Asruf Uz Zaman said gas was not being supplied to Khulna even though there was a great demand for gas there.
“It is very unfortunate that the gas line has been installed but the residential subscribers in Khulna are not going to get the gas,” he said.
He urged the government to provide the consumers in Khulna with gas connection if the government is able to unearth new gas reserves.
Sundarban Gas MD Khalequzzaman said even if this project was closed, new ones would be taken up to provide commercial and industrial gas connections with the government's approval.
The Sundarban Gas headquarters will be constructed under a different project, he said.