Botched road repair prolongs Bishwanath residents' misery

  • Published at 01:19 pm August 5th, 2021
Sylhet road-UNB
A rundown portion of a 13-km road in Bishwanath, Sylhet that has been undergoing repair works for one-and-half years UNB

Heavy showers cause waterlogging in the road making it even more dilapidated and causing untold sufferings to locals

The repair works of a 13-km road in Bishwanath, an upazila of Sylhet, has now gone on for one-and-half years. Not only is the repair project incomplete - serious questions remain over the quality of work that has been completed.

At present, work on the repair project has come to a standstill, with about half the 13-km road stretching from Bishwanath GC to the edge of Jagannathpur repaired (for what it's worth). Numerous potholes can be seen on the other half of the road.

Heavy showers cause waterlogging in the road making it even more dilapidated and causing untold sufferings to pedestrians in particular, who frequent this route.

The authorities approved the repair project on December 17, 2019. Contractor Shaon Enterprise got the tender with an allocation close to Tk23.47 crore. 

RCC slab casting, a form of concrete casting, was estimated to be needed on about 18m in different parts of the 13.09 km road.

However, the contractor took six months from the approval to start the work - among other things, the pandemic caused delays.

After working for a few days, they stopped working for another three to four months due to personal reasons. In this situation, when the tender was about to be cancelled, the contractor shifted the responsibility of the repair work to his other associates.

The locals said: "If the work had started on time, we would not have suffered. As half of the road remained incomplete, the road has become more dilapidated due to waterlogging caused by monsoon rains. Potholes are everywhere on the road."

There are also many defects in the completed part of the road.

At present, the work has been in limbo for six-to-eight weeks. In this situation, there is uncertainty about the rest of the repair work.

Upazila Engineer Abu Saeed told UNB that about half of the repair work has been completed. According to his office, about seven to eight metres of RCC casting remains.

Apart from that, 9 km of sub-base (pavement), 8 km of Dabu BM (bitumen) and 5 km of carpeting have been completed. The remaining half of the work is unfinished.

"If the lockdown is eased, the work will be completed as soon as possible with an increased number of labourers," Engineer Saeed insists. But the long-suffering residents can only doubt his reassurances.

50
Facebook 50
blogger sharing button blogger
buffer sharing button buffer
diaspora sharing button diaspora
digg sharing button digg
douban sharing button douban
email sharing button email
evernote sharing button evernote
flipboard sharing button flipboard
pocket sharing button getpocket
github sharing button github
gmail sharing button gmail
googlebookmarks sharing button googlebookmarks
hackernews sharing button hackernews
instapaper sharing button instapaper
line sharing button line
linkedin sharing button linkedin
livejournal sharing button livejournal
mailru sharing button mailru
medium sharing button medium
meneame sharing button meneame
messenger sharing button messenger
odnoklassniki sharing button odnoklassniki
pinterest sharing button pinterest
print sharing button print
qzone sharing button qzone
reddit sharing button reddit
refind sharing button refind
renren sharing button renren
skype sharing button skype
snapchat sharing button snapchat
surfingbird sharing button surfingbird
telegram sharing button telegram
tumblr sharing button tumblr
twitter sharing button twitter
vk sharing button vk
wechat sharing button wechat
weibo sharing button weibo
whatsapp sharing button whatsapp
wordpress sharing button wordpress
xing sharing button xing
yahoomail sharing button yahoomail