• Thursday, Sep 16, 2021
  • Last Update : 10:01 pm

Govt fails to take power from Payra plant, counts huge loss in capacity payment

  • Published at 05:50 pm July 30th, 2021
Payra Thermal Power Plant
Aerial view of the coal-fired Payra Thermal Power Plant in Patuakhali, Bangladesh Dhaka Tribune

The project has hit some hurdles in crossing the mighty Padma river

The government is counting a monthly loss of Tk130 crore due to the delay in laying a high-priority transmission line that would take electricity from the Payra power plant to Dhaka across the Padma River.

According to official sources, the amount is being paid as “capacity payment” to the 1,320MW Payra power plant, a Bangladesh-China joint venture project, which is now ready to supply electricity to the national grid for distribution in Dhaka adjoining areas.

In this case, the capacity payment means the government’s commitment to purchase power generated at the plant at an agreed-upon rate. The government still has to pay the plant for its generation (capacity) even if it is unable to buy electricity from it.

The government is not ready to purchase electricity from the plant as it has failed to complete work on the 164.6 km 400 kV double-circuit transmission line that would supply power from Mongla to Dhaka’s Aminbazar via Mawa connected by the national grid.

The project has hit some hurdles in crossing the mighty river, where a multipurpose bridge is being built to connect Dhaka with the country’s southwestern region.

The official document of the Power Grid Company of Bangladesh (PGCB), the implementing agency, shows the project was scheduled to be implemented by December 2020. After repeated extensions, the schedule has now been set for December 2021. 

Officials, however, apprehend the project might not be completed even by the latest deadline due to a major constraint in the work on crossing the Padma River.

Nasrul Hamid, state minister for power, energy and mineral resources, acknowledged the loss government is incurring and the hurdles the project is facing.

“We are trying to resolve the issue,” he told UNB adding “We have nothing else to do but to  wait.”

Power Division officials blamed the excessive delay on the Padma Bridge construction authority which was tasked to lay foundations for the construction of towers within the river area.

The government took up the Tk 2505.37 crore Aminbazar-Maowa-Mongla project in 2016 targeting power evacuation from two large power plant projects —1320 MW Rampal and 1320 MW Payra coal-fired power plants—for Dhaka and adjoining areas.

As per the design, the 164.6 km transmission line will directly bring electricity from the Rampal plant, while power from the Payra plant will come to Dhaka through this line using facilities in the Gopalganj power transmission hub. 

To make this happen, officials said, a separate transmission line between Payra and Gopalganj has already been built and it is now in operation. 

“But the Mongla-Maowa- Aminbazar project remained stuck up at the 9.4 km Padma River crossing portion”, said the PGCB official adding that a total of 11 towers will be built in this portion of the line of which 7 towers will be installed within the river area. 

“The responsibility of towers’ foundation work in the deep of the river was given to the Padma Bridge Authority”, said PGCB Managing Director Golam Kibria adding that they have been trying to do the job. 

He said the Padma Bridge Authority has recently informed that they will now complete the foundation work of the first tower in August this year. Work on the remaining foundations will be done by April next year before handing the sites over to the PGCB.

He noted that PGCB plans to start the tower installation and other works as soon as it receives the sites from Padma Bridge Authority. 

“The tower installation and other works may take up to December next year”, he said adding that the PGCB will try its best to do the job as early as possible. 

Official sources said the government has to continue the capacity payment of Tk130 crore per month until start of full swing evacuation of power from the Payra plant as an obligation of the power purchase agreement (PPA).

Half the output from the 660MW plant is being supplied to the national grid’s South and Eastern region for the non-completion of the Aminbazar-Mawa-Mongla transmission project. 

“So, the delay in transmission project’s execution means the cost escalation in the guise of capacity payment”, said a PGCB official.    

They said the capacity payment would be even double if the first unit of the Rampal power plant comes into commercial operation as scheduled in December this year.

Officials said the Rampal power plant is being constructed in a joint venture with India while the Payra power plant was built under a joint venture with China.

Both the plants started construction works in December 2017. But Payra successfully completed construction of its two units as per schedule, but Rampal failed to install the first unit as yet, they noted. 

Payra plant’s officials said they have been operating the two units in alternative months to keep the plant’s equipment operational.

159
Facebook 149
blogger sharing button blogger
buffer sharing button buffer
diaspora sharing button diaspora
digg sharing button digg
douban sharing button douban
email sharing button email
evernote sharing button evernote
flipboard sharing button flipboard
pocket sharing button getpocket
github sharing button github
gmail sharing button gmail
googlebookmarks sharing button googlebookmarks
hackernews sharing button hackernews
instapaper sharing button instapaper
line sharing button line
linkedin sharing button linkedin
livejournal sharing button livejournal
mailru sharing button mailru
medium sharing button medium
meneame sharing button meneame
messenger sharing button messenger
odnoklassniki sharing button odnoklassniki
pinterest sharing button pinterest
print sharing button print
qzone sharing button qzone
reddit sharing button reddit
refind sharing button refind
renren sharing button renren
skype sharing button skype
snapchat sharing button snapchat
surfingbird sharing button surfingbird
telegram sharing button telegram
tumblr sharing button tumblr
twitter sharing button twitter
vk sharing button vk
wechat sharing button wechat
weibo sharing button weibo
whatsapp sharing button whatsapp
wordpress sharing button wordpress
xing sharing button xing
yahoomail sharing button yahoomail