• Friday, May 14, 2021
  • Last Update : 01:02 pm

What revisions were done in Padma Bridge Rail Link design?

  • Published at 07:53 pm December 3rd, 2020
The-under-construction-Padma-Bridge_02.12
The under-construction Padma Bridge, on Wednesday, December 2, 2020 Mehedi Hasan/Dhaka Tribune

The construction work at the problematic points of the rail link, which was suspended due to issues in the design, will resume soon, says railways minister

The Bangladesh Railway (BR) has already fixed the design flaw of the Padma Bridge Rail Link Project (PBRLP), but construction work at the problematic areas has yet to resume.

“There is no design flaw actually. We found a problem at the crossing points of the PBRLP, which has already been fixed,” Railways Minister Nurul Islam Sujan has said.

A recent visit to the site, however, revealed that the construction work was at a standstill at both points of the design flaw. 

If the construction work is not resumed immediately, the cost of the project might increase and, on top of that, the authorities may not be able to meet the deadline of the launch of train services on the opening day of the Padma Multipurpose Bridge, scheduled for next year.

Even so, the railways minister assured that the construction work would soon resume and there was no need to be apprehensive about an increase in cost or required time.

“We are optimistic that trains will be operated on the inauguration day of the Padma Multipurpose Bridge,” Sujan told Dhaka Tribune. 

According to the existing design of the PBRLP, the rail link would have obstructed the movement of road traffic on the approach roads to the Padma Bridge at both ends — Mawa and Janjira.

A segment of the Padma Bridge rail link. Construction of this segment of the project is currently suspended, due to some flaw in the project design. The construction work is supposed to resume soon, according to Railway Ministry officials. The photo was taken on Wednesday, December 2, 2020 | Mehedi Hasan/Dhaka Tribune

The railways minister said: “We have decided to adjust some railway pillars accordingly to ensure that there will be no traffic barriers.”   

According to the Bridges Division, the height of the rail line was set at 4.8m and 5.2m at Mawa and Janjira, respectively, instead of the standard height of 5.7m. Furthermore, the width of the rail link was shown as 9.5m at Janjira and 10m at Mawa, instead of the standard 15.5m.

To overcome these difficulties, BR has held a series of meetings with the Bridges Division as well as the Roads and Highways Department since the problem was identified in August. Initially, BR was in favour of slightly increasing the height and width but later it took into consideration the standard height and width for traffic movement.

Regarding this issue, the railways minister said: “We have fixed the problem by going for the standard height and width — 5.7m and 15.5m; some of the railway pillars might need restructuring.”


Also read - Automated sleeper factory to speed up Padma Bridge Rail Link Project


“Two or three pillars at the Mawa point likely need to be restructured. But there is no restructuring needed at the Janjira point as no pillar has been installed there yet. We’ll set up an additional pillar at the latter point to solve the issues,” Sujan said. 

BR took the decision following recommendations made by the government's expert panel on the Padma Multipurpose Bridge Project.

‘No need for major structural changes’

Echoing the railways minister’s words, Prof Shamim Z Bosunia, chairman of the expert panel, said: “It is not a massive design flaw and hence there is no need for major structural changes.”

“We basically identified an alignment fault in the PBRLP where the Padma Bridge and the rail link cross each other,” he added.

“While constructing the piles of the Padma Bridge, we faced many difficulties which were eventually resolved. It is not a fault at all,” Shamim told Dhaka Tribune.

“As far as I know, Bangladesh Railway has already made the necessary structural changes,” he added.

The Padma Bridge Rail Link will be the main transportation channel connecting central Bangladesh with the western and south-western parts of the country, across the Padma Multipurpose Bridge, by June 2024 at a cost of Tk39,246 crore.

The government plans to open a section of the rail route — the 14km Mawa and Bhanga portion of the 168.6km long rail link — in 2021. The new rail link will shorten current travel distance between the capital, Jessore and Khulna, by 308km.

54
Facebook 52
blogger sharing button blogger
buffer sharing button buffer
diaspora sharing button diaspora
digg sharing button digg
douban sharing button douban
email sharing button email
evernote sharing button evernote
flipboard sharing button flipboard
pocket sharing button getpocket
github sharing button github
gmail sharing button gmail
googlebookmarks sharing button googlebookmarks
hackernews sharing button hackernews
instapaper sharing button instapaper
line sharing button line
linkedin sharing button linkedin
livejournal sharing button livejournal
mailru sharing button mailru
medium sharing button medium
meneame sharing button meneame
messenger sharing button messenger
odnoklassniki sharing button odnoklassniki
pinterest sharing button pinterest
print sharing button print
qzone sharing button qzone
reddit sharing button reddit
refind sharing button refind
renren sharing button renren
skype sharing button skype
snapchat sharing button snapchat
surfingbird sharing button surfingbird
telegram sharing button telegram
tumblr sharing button tumblr
twitter sharing button twitter
vk sharing button vk
wechat sharing button wechat
weibo sharing button weibo
whatsapp sharing button whatsapp
wordpress sharing button wordpress
xing sharing button xing
yahoomail sharing button yahoomail