Dhaka-Cox’s Bazar rail project: What's causing construction delay?

  • Published at 11:45 pm September 4th, 2021

Deadline likely to be extended to June 2023

Much to the dismay of travellers who were looking forward to visiting Cox’s Bazar by train next year, many impediments are yet holding up the rail project, which is a hint that it will not reach completion even by the end of 2022.

Construction work of the single-line dual gauge railway track from Dohazari in Chittagong to Cox’s Bazar has been delayed not only due to the Covid-19 pandemic but also owing to a lack of coordination among the agencies concerned.

Bangladesh Railway (BR) officials told Dhaka Tribune that they were still unable to resolve issues regarding land acquisition, electricity line transfer and import of construction materials from India, Malaysia and China.

BR, the implementing agency of the 102km railway line project, has applied to the Planning Commission for an extension of the project deadline to June 2023.

“We have already put in an application for the deadline to be extended as the pandemic and some other major challenges have been hindering the progress of the project,” said Md Mofizur Rahman, director of the rail project.

Major challenges

The 102km Dohazari-Cox’s Bazar rail link is being implemented under two lots, at a cost of Tk18,035 crore.

China Railway Group Ltd (CREC) and Toma Construction JV are have been assigned Lot-1, from Dohazari to Chakaria (50km), while China Civil Engineering Construction Corporation (CCECC) and Max Group JV are responsible for Lot-2, from Chakaria to Cox’s Bazar (52km).

According to BR, overall progress of the project was 62% till August 31, far below the target.

The construction work of the single-line dual gauge railway track from Chittagong to Cox’s Bazar has been delayed due to Covid-19 pandemic | Courtesy

According to the revised agreements, the contractors are committed to complete their work by January 31, 2023, and BR is scheduled to start operations by June 2023.

CCECC Project Manager Chen Yongyi said “The organization was facing difficulties during construction work due to not getting access to sites as many landowners had yet to receive compensation from the government, slow relocation of the power grid line, issues regarding tree-cutting in forest areas and the Covid-19 pandemic.”

The project had been progressing slowly despite CCECC helping BR resolve some of the issues, he said.

“We are continuing with the construction work even amid the pandemic by adhering to hygiene rules as we want to complete the task within the deadline,” he added.

Project Manager Md Farhad Hossain of Max Infrastructure Ltd said that some construction work needing to be done outside the contract had been causing further delay.

Meanwhile, Md Mofizur Rahman, director of the Dohazari to Cox’s Bazar rail project, said that everyone involved with the project was working sincerely to resolve the issues confronting the project.


Also Read - Dhaka-Cox’s Bazar train service expected to augment tourism prospects


“The administration in Chittagong and Cox’s Bazar has all but completed the land acquisition process,” he said.

Work to relocate the power grid line would start soon as well, Mofizur Rahman said.

He attributed the problems regarding import of materials to pandemic-induced closures.

Swift journeys

Some five million tourists visit Cox’s Bazar every year. Once completed, the rail link will facilitate their swift travel to the world’s longest sea beach not only from the capital Dhaka, but also from neighbouring Bhutan, India and Nepal through the existing Dhaka-Kolkata rail route. The rail link will also be connected with the under-construction Akhaura-Agartala rail route.

Travellers from Dhaka will be able to reach Cox’s Bazar in only six hours — four hours quicker than the current fastest road route. Meanwhile, the journey from Kolkata will take 16 hours, according to project documents.

The new link will also be part of the Trans-Asian Rail network, connecting Bangladesh with other regional neighbours, including China, Myanmar and Thailand.

109
Facebook 78
blogger sharing button blogger
buffer sharing button buffer
diaspora sharing button diaspora
digg sharing button digg
douban sharing button douban
email sharing button email
evernote sharing button evernote
flipboard sharing button flipboard
pocket sharing button getpocket
github sharing button github
gmail sharing button gmail
googlebookmarks sharing button googlebookmarks
hackernews sharing button hackernews
instapaper sharing button instapaper
line sharing button line
linkedin sharing button linkedin
livejournal sharing button livejournal
mailru sharing button mailru
medium sharing button medium
meneame sharing button meneame
messenger sharing button messenger
odnoklassniki sharing button odnoklassniki
pinterest sharing button pinterest
print sharing button print
qzone sharing button qzone
reddit sharing button reddit
refind sharing button refind
renren sharing button renren
skype sharing button skype
snapchat sharing button snapchat
surfingbird sharing button surfingbird
telegram sharing button telegram
tumblr sharing button tumblr
twitter sharing button twitter
vk sharing button vk
wechat sharing button wechat
weibo sharing button weibo
whatsapp sharing button whatsapp
wordpress sharing button wordpress
xing sharing button xing
yahoomail sharing button yahoomail