Three local private companies have proposed to set up five power projects of total 2300 megawatt in Chittagong, nearly half of which will be generated from costly furnace oil.
Summit Power Limited, United Power Generation and Distribution Co. Ltd and a joint-venture consortium of Bangla Trac Communication and Acron Infrastructure Services Ltd submitted the proposals to Power Division recently.
Furnace oil-based plants cost Tk16 for a unit of electricity while the coal-based plants cost Tk6 and the gas-based plants cost Tk2 for a unit.
Power Development Board (PDB) officials said as the government has extended the tenures of nine rental power plants, there is no need of heavy fuel oil (HFO)-based power plants. HFO is known as furnace oil.
“We have received proposals from three companies to build five power plants in Chittagong. They can be considered,” Power Secretary Monowar Islam told the Dhaka Tribune yesterday.
But the government’s possible consideration has greatly astonished the PDB high officials as they see no necessity of any new costly plant now.
Three HFO-based and two Liquefied Natural Gas (LNG)-based plants have been proposed by the companies.
Of them, Summit wants to construct 500MW HFO-based and 700MW LNG-based plants, United proposes to set up 500MW HFO-based and 500MW LNG-based plants and the joint venture seeks permission for 100MW HFO-based plant.
“All the proposals have been sent to the PDB for evaluation. If PDB is positive about the projects, the proposals will be sent to the cabinet committee on public purchase for approval,” he said.
PDB sources said the country already has such plants with a total of 1963MW generation capacity and this capacity is 19.17% of the country’s total power generation capacity.
More 15 HFO-based power projects are under construction now in public and private sectors and the total capacity of these plants is around 1400MW.
Besides, tenders are under process for more six furnace oil-based projects with 900MW capacity.
If all these plants come to operation, the furnace oil-based generation will exceed 5000MW.
Further, the country has diesel-run power plants with a generation capacity of 683MW which is 6.67% of total capacity.
Power Division initially decided not to extend tenure of any expensive rental and quick rental plants.
But as commencement of the less costly based-load power projects were delayed, the division extended the tenures of nine rental and quick rental plants.
According to the proposals, the five projects will be run as independent power producers (IPPs) on build, own and operate (BOO) basis. The companies will import fuel at their own arrangement to operate the plants.
The government earlier cancelled deal to install Summit’s Bibiyana-1 341MW combined-cycle power project because of the company’s failure to complete the plant within deadline.
Summit’s Bibiyana-2 341MW combined-cycle power project also missed its previous deadline which was August, 2013.
The deadline for Bibiyana-2 project has been reset for December, 2014.
Besides, the 335MW Meghnaghat combined-cycle power project of Summit was scheduled to begin generation also in August 2013, but missed the deadline. Now the Summit officials are expecting to start the plant’s generation by April, 2014.
Summit Power is a company under Summit Group and United Power Generation belongs to United Group.
Summit Group operates a total of 11 power plants currently having 573.55MW power generation capacity while the United Group has two power plants with a total of 170MW capacity. Acron has one power plant of 100MW.