Climate project raises question among local representatives

Public representatives in Khulna’s Koira and Dacope upazilas expressed dissatisfaction over the implementation of an internationally funded climate project in the area, questioning the project’s transparency.

Several local administration officials claimed to have no knowledge of the project’s plan or progress while talking to the Dhaka Tribune. “I have seen electric net fences set up around many chars [shoals] in my union. I don’t know why it was done; I was not notified about it,” complained Abdul Mannan, chairman of South Bedkashi union parishad in Koira.

The project, titled Climate Resilient Ecosystems and Livelihoods (CREL), is being implemented by US-based Winrock International and some associate organisations. Funded by the USAID, the five-year, Tk300-crore project is aimed at developing the capacity to counter the affects of climate change in Khulna, Sylhet, Chittagong and Cox’s Bazar and develop better, environment-friendly life and livelihoods for the locals.

Sources said since the project’s work in the two upazilas started in late 2013, its progress has been rather slow.

The only visible work seems to be kilometres of electric net boundaries set up in places, parts of which have already started to get damaged.

“What good will the electric net fences will do for the local population’s development? The project planners have not talked to any of the local leaders in this regard,” claimed Sardar Motiar Rahman, chairman of North Bedkashi union parishad in Koira.

However, local official of the project, Babul Islam, said the boundaries were set up to protect the area surrounding the Sundarbans as well as 85 hectares of shoals.

“We have also planted saplings in different academic institutions. A committee have been formed for their maintenance, which includes local residents,” he told the Dhaka Tribune on Sunday.

Talking to the Dhaka Tribune on Wednesday, Koira Upazila Nirbahi Officer Md Shamim Osman said: “I was made an adviser to the project implementation committee. If the project is implemented exactly how its plan was presented to us, it will have a significant effect in developing the life and livelihood of the locals. However, I have yet to get a clear understanding as to how well the project is being executed in real life.”

Sheikh Md Ziaul Haq, regional project coordinator, said the project was being implemented with the assistance of the Forest Department, the local representatives and administrations.

However, when asked about the amount of fund allocated for Dacope and Koira, he declined to comment.

Md Osman Gani, general secretary of the project management committee for Dacope and Koira, said there has been some progress in Koira, but the process for Dacope was still at the planning stage. “We have yet to be certain as to how the project should progress.”