With less than two months remaining for the competition of Dasherkandi sewerage treatment plant, Dhaka Water Supply and Sewerage Authority (DWASA) is yet to even begin work on the project due to a lack of sufficient funds.
The water quality of the Hatirjheel-Begunbari canal is worsening with every day of delay in the construction of the plant.
According to the Local Government Department (LGD), the installation of the waste treatment plant at the cost of Tk425 crore was scheduled to begin in January 2011 and end in December 2013.
Prime Minister Sheikh Hasina on November 7 told parliament that DWASA has already undertaken a state-of-the art project titled ‘Treatment Plant at Dasherkandi for Treating Divested Sewage from Hatirjheel and Begunbari canal’.
However, DWASA Deputy Managing Director (Admin) Md Ataur Rahman told the Dhaka Tribune the installation of the Dasherkandi sewage treatment plant “is delayed due to lack of sufficient money for the project.” He claimed the state-run agency does not have enough money to implement a big project like the Dasherkandi plant.
“World Bank gave $76m to DWASA to improve the city’s water supply and sewerage management. The WB also told us, if we spend this money properly, they will give us $200-300m for the development the sector” he said.
“We are spending the money properly, and we hope we will also get the proposed fund of WB” he added.
The Hatirjheel-Begunbari integrated development project aims to conserve rain water, improve the water quality in the canal, reduce water-logging in the capital and maintain environmental balance.
Prof Mujibur Rahman of Bangladesh University of Engineering and Technology (BUET), who is also team leader of BRTC, BUET for Hatirjheel project, said they had made the Hatirjheel project’s drawing design and the feasibility study, and already completed the study design of Dasherkandi plant and sent it to the DWASA authority.
“The waste treatment plant has been designed to treat 6 lakh cubic metres of water per day. To disposal 10.45 crore cubic metres of sewage of adjoining areas of around the Hatirjheel-Bagunbari, 10.40km main diversion and 7.7km local diversion swear line had to be added in to the project design,” he said.
He also said sewage comes from different pipe lines, and it will drain by the sewer lines and go to Dasherkandi treatment plant. So after competition of the project, water Hatirjheel-Begunbari canal will be more improved than its present condition.
The sewage treatment plant will be constructed on 60 acres of land in Dasherkandi, in the capital. Hatirjheel-Begunbari canal connects with the river Balu, which later joins the Shitalakkhya River and so with this canal getting polluted the water of the two rivers.
AKM Shahid Uddin, project director of DWASA for the Hatirjheel project said: “More time will be needed to improve the water quality of the lake. It will also not be overcome before completion of the Daserkandi sewage treatment plant.”