‘Tannery Industrial Estate to start functioning next year’

The long-awaited shifting of Hazaribagh’s leather industries to Savar is likely to start next year as the government took a fresh move to keep the Tannery Industrial Estate, Dhaka, ready by 2014.

“We have identified various hurdles regarding the shifting. We will now fix a timeframe to start the shifting process of leather industries and I hope we will be able to keep the estate ready by next year,” Industries Minister Dilip Barua told BSS Saturday.

Barua said currently, the contractor of the project will start the construction of the Central Effluent Treatment Plant (CETP) and the dumping ground.

He said the cost of the project had already been increased due to change in the value of US dollar and the delay in setting up the park and other necessary facilities.

He further said the project’s design had recently been revised where new features like electricity production and sewerage system had been included.

Under the “Tannery Industrial Estate, Dhaka (2nd revised) Project”, the government will develop industrial plots with adequate infrastructural facilities for private entrepreneurs, build the CETP and dumping yard for waste management.

According to the latest revision, the project cost standing at Tk10.78bn will ensure the setting up of the CETP and all other facilities by June 2016.

Under the project, 205 plots were developed which have already been distributed among the owners of 155 factories located at Hazaribagh in the city.