CDA fails to initiate road project even after 8 years

The Chittagong Development Authority (CDA) has yet to initiate the construction of an Outer Ring Road around the town protection embankment, despite it being eight years since the Tk8.56b-project was embarked on in 2005.

According to sources, the Japan International Cooperation Agency (Jica) is supposed to provide Tk6.9b of the total project value, while the government of Bangladesh is to provide the rest of the funds.

So far, CDA had only finalised the design of the four-lane road, but vital matters such as land acquisition to relocate people living around the dam are still pending.

There are approximately 12 thousand people living near the dam now. 

Kazi Hasan Bin Shams, a superintendent engineer of CDA and the director of the project, said they had selected three sites – at Patenga, Khejurtola and the Sagarika Stadium area – for relocating the people currently inhabiting the dam site.

He, however, said that no proposal about land acquisition has yet been sent to the district administration, but “it would be done by this month.”

He further said the outlay of the project would increase significantly due to the delay in its implementation, with prices of construction materials and other essentials having risen since June 2005. 

“Considering the cost, I think we should construct a two-lane road for now, keeping the option open to turn it into four lanes at a later time,” he added.    

Abdus Salam, chairman of CDA, told the Dhaka Tribune that they would soon initiate the process of acquiring necessary land and rehabilitate the people in question, adding that they were “optimistic” about floating an international tender for the construction of 15-kilometer road by the coming September.

“Implementation of the project will play a significant role in easing traffic congestion in the city, as sizeable numbers of vehicles heading to and away from the airport and the Chittagong Export Processing Zone will be able to use this alternative route,” he said.

When asked about the delay in initiating the project, the CDA chairman said they had to take time because of the difficulties they faced “in selecting sites” for the rehabilitation of the people on the embankment.

“We just wanted to make sure that they would be rehabilitated in places better than their current places of residence. I believe the three places that we have selected for them would be highly appreciated.”