The revised cost of the API (active pharmaceutical ingredients) Park project has increased substantially from its original estimate due to extension of project duration owing to delay in land acquisition, re-estimation following new rate schedule and adding new component.
The cost now stands at Tk332 crore, an increase of more than 55% from original outlay of Tk213 crore. Its first revision project cost was TK233 crore. The work on the project was scheduled to commence in January 2008 and complete by December 2012.
With this second revision of the industrial park dedicated for pharmaceutical products, a total of five development projects worth Tk640 crore were approved at a meeting of the Executive Committee of the National Economic Council (Ecnec) at NEC conference room yesterday, with Prime Minister Sheikh Hasina in the chair.
Briefing reporters after the meeting, Planning Minister AHM Mustafa Kamal said of the total expenditure, Tk558 crore will come from the government fund and the remaining Tk82 crore from own funds of the organisations.
The revision of the pharmaceutical park project was due to project time extension, delay in land acquisition, re-estimation following new rate schedule and adding new component to the project, officials sources said.
Under this project, an API Park would be set up on a 200-acre area at Gazaria, Munshiganj district, with a capacity to accommodate industrial units on 42 plots to produce active pharmaceutical ingredients.
Replying to a question on possible cut in the revised development budget for the current fiscal year, the Planning Minister said they are trying
to increase the allocation, not curtailing it. He said the ministry would work on keeping close monitoring with the line ministries to increase implementation of the ADP.
So far, some 157 projects in the current fiscal year were approved at the Ecnec meeting, including 97 new projects and 60 ongoing projects with an outlay of Tk95,829 crore.
Of the amount, Tk54,817 crore will come from the government fund and Tk38,237 crore as project assistance, apart from Tk2,775 crore from the organisations.